Location Project Title Description of Work or Service Estimated Start of Works Date Estimated Completion Date Estimated Value of Work HA Project Sponsor HA Procurement Officer Details of Contractors Comments Box North East A66 Little Burdon to Bewley Hill Resurfacing
The extent of the works are on the A66 Dual Carriageway from Little Burdon to Long Newton. The works involve the removal and replacement of carriageway to a depth of 300mm and 100m for Lanes 1&2 respectively.
December 2011 March 2012 £2,439,099.27 Andrew Brown Julie Askham Hanson Contracting, Ashby Road East, Shepshed, Leicestershire, LE12 9BU This contract was awarded on 2nd December 2011. North East A1 Morpeth Cutting Stabilisation The works involve designing and installing sheet piles into embankment to stabilise the slope and prevent slips. Along with the sheet pile installation the works include preparatory site clearance and traffic management, with a 24/7 contraflow being in operation. 6th February 2012 24th March 2012 £1.2m Nick Adshead Karen Evans Balfour Beatty Regional Civil Engineering This contract was awarded on the 18th November 2011 North East A19 Middle Engine Railway & Middle Engine Lane Bridge Refurbishment Work The proposed works to the bridges include (i) infilling the cellular abutments with lightweight concrete and grout (ii) drilling and grouting steel strengthening bars into the front faces of each abutment (iii) replacing the longitudinal, centreline, deck joints on both bridges and (iv) replacing the transverse deck joints on both bridges
5/12/11 March 2012 £446,514 Shaun Cullumbine Dave Harvey Balfour Beatty Regional Civil Engineering This contract was awarded on the 7/11/11 North East A1 Capri Lodge Resurfacing of both the North and Southbound carriageway October 2011 November 2011 £917,546.00 Nick Adshead Laura Watson Hanson Contracting South East Dartford Crossing Ventilation Fans/Variable Speed Drives Construction operation. Contract for ventilation fans & Variable speed drives. February 2010 September 2011 £651,334.00 Paul Harding Gay McBride TayWest Control Systems Ltd., St Augustine Bus. Park, Estuary Close, Swalecliffe, Whitstable CT5 2QJ HA Ref: 13/532693 South East Dartford Crossing West Tunnel Lining Installation of fire retardant crown lining to West Tunnel. March 2010 August 2011 £3,463,010.69 Paul Harding Gay McBride Sharpfibre Ltd, 4 Braiswick Place, Laindon North Ind. Centre, Laindon , Essex SS15 6EB HA Ref: 13/5/2693 South East Dartford Crossing Wayfinder Lights & Escape Signage Installation of Wayfinder Lights & Escape Signage within the tunnels. March 2010 March 2013 £1,865,345.02 Paul Harding Gay McBride Southern Electric Contracting Ltd, Unit 5, Crompton Fields, Crompton Way, Crawley. RH10 9QB HA Ref: 13/5/2697
South East Dartford Free Flow Charging 1. Provide strategic Business Case. 2. Provide Procurement Strategy. 3. Provide Programme of Works for the introduction of Free Flow Charging at the Dartford Crossing. September 2010 December 2010 £99,000.00 Gary Bacon Gay McBride Deloitte LLP, Stonecutter Court, Stonecutter Street, London EC4A 4TR
HA Ref:13/5/3715 South East Dartford Crossing EUD Incident Detection System Incident Detection System/Cameras within Dartford Tunnel to be linked to Fire Suppression System January 2012 September 2013 £1,654,612.73 Paul Harding Laurence Potts Vital Services Group Ltd, Vital Resources, Gresham Mill, South Hall Street, Salford M5 4TP This contract was awarded on 30/01/12 South West A35 Weymouth & Stinsford Roundabout Improvement Road Improvement Sept 2010 April 2011 £2.1m Alexis Wood Tony Ballinger Birse Civils Ltd, Western Region, Stonehouse Business Park, Sperry Way, Stonehouse, Glos, GL10 3UT HA Ref: 13/5/2549 East A14 Orwell Bridge Phase 4 Bearing Replacement Replacement of Bearings June 2010 Nov 2010 £1,100,855 Nicholas Royse Alan Procter Jackson Civil Engineering Group Ltd
30 White House Road, Ipswich, Suffolk, IP1 5LT
HA 13/1/846 (PE 796) North East A184 Whitemare Pool to Testos Roundabout Full resurfacing of both East and Westbound carriageways September 2011 October 2011 £676,893 Steve Bishop Laura Watson Tarmac Ltd North East A66 Cross Lanes to Rokeby Resurfacing Removal and replacement of 85mm of pavement (small areas 300mm). The works will be carried out on night shifts only, with traffic signals and convoy working. October 2011 October 2011 £761,064.00 Andrew Brown Karen Evans Tarmac Ltd. South West 13/5/3765
A38 Drumbridges to Goodstone resurfacing
Resurfacing contract October 2011 November 2011 £930,000 Alexis Wood Jason Prichard Hanson Contracting 13/5/3765
North East A19 Moor Farm to Killingworth Carriageway ResurfacingResurfacing contract October 2011 November 2011 £906,330.00 Shaun Cullumbine Dave Harvey Tarmac Limited South West 13/5/3764
A30 Five Mile Hill
The Scheme will involve the stabilisation of 180m length of the embankment which supports the eastbound carriageway. The embankment varies from 13m to 20m in height with side slopes of approximately 1:2(v:h) and has been constructed from locally won shales of the Upper Carboniferous Crackington and Ashton Shale Formations January 2012 April 2012 £1,031,418.41 Alexis Wood Jason Prichard Birse Civils