Current Schemes Below OJEU Threshold

Last updated: September 2011

Location Project Title Description of Work or Service Estimated Start of Works Date Estimated Completion Date Estimated Value of Work HA Project Sponsor HA Procurement Officer Details of Contractors Comments Box
North East   

A66 Little Burdon to Bewley Hill Resurfacing

 

The extent of the works are on the A66 Dual Carriageway from Little Burdon to Long Newton. The works involve the removal and replacement of carriageway to a depth of 300mm and 100m for Lanes 1&2 respectively.

 December 2011  March 2012  £2,439,099.27  Andrew Brown  Julie Askham  Hanson Contracting, Ashby Road East,  Shepshed, Leicestershire, LE12 9BU  This contract was awarded on 2nd December 2011.
North East   A1 Morpeth Cutting Stabilisation  The works involve designing and installing sheet piles into embankment to stabilise the slope and prevent slips. Along with the sheet pile installation the works include preparatory site clearance and traffic management, with a 24/7 contraflow being in operation.  6th February 2012  24th March 2012  £1.2m   Nick Adshead  Karen Evans  Balfour Beatty Regional Civil Engineering  This contract was awarded on the 18th November 2011
 North East  A19 Middle Engine Railway & Middle Engine Lane Bridge Refurbishment Work  

The proposed works to the bridges include (i) infilling the cellular abutments with lightweight concrete and grout (ii) drilling and grouting steel strengthening bars into the front faces of each abutment (iii) replacing the longitudinal, centreline, deck joints on both bridges and (iv) replacing the transverse deck joints on both bridges

 5/12/11  March 2012  £446,514  Shaun Cullumbine  Dave Harvey  Balfour Beatty Regional Civil Engineering  This contract was awarded on the 7/11/11
North East   A1 Capri Lodge  Resurfacing of both the North and Southbound carriageway  October 2011  November 2011  £917,546.00  Nick Adshead  Laura Watson  Hanson Contracting  
South East  Dartford Crossing Ventilation Fans/Variable Speed Drives  Construction operation. Contract for ventilation fans & Variable speed drives.  February 2010 September 2011 £651,334.00  Paul Harding Gay McBride  TayWest Control Systems Ltd., St Augustine Bus. Park, Estuary Close, Swalecliffe, Whitstable CT5 2QJ   HA Ref: 13/532693
 South East  Dartford Crossing West Tunnel Lining Installation of fire retardant crown lining to West Tunnel.  March 2010 August 2011 £3,463,010.69   Paul Harding Gay McBride   Sharpfibre Ltd, 4 Braiswick Place, Laindon North Ind. Centre, Laindon , Essex SS15 6EB  HA Ref: 13/5/2693
 South East Dartford Crossing Wayfinder Lights & Escape Signage  Installation of Wayfinder Lights & Escape Signage within the tunnels.   March 2010 March 2013  £1,865,345.02  Paul Harding Gay McBride  Southern Electric Contracting Ltd, Unit 5, Crompton Fields, Crompton Way, Crawley. RH10 9QB 

 HA Ref: 13/5/2697  

South East   Dartford Free Flow Charging 1. Provide strategic Business Case. 2. Provide Procurement Strategy. 3. Provide Programme of Works for the introduction of Free Flow Charging at the Dartford Crossing.  September 2010  December 2010 £99,000.00  Gary Bacon  Gay McBride 

Deloitte LLP, Stonecutter Court, Stonecutter Street, London EC4A 4TR 

HA Ref:13/5/3715 
South East  Dartford Crossing EUD Incident Detection System  Incident Detection System/Cameras within Dartford Tunnel to be linked to Fire Suppression System  January 2012  September 2013  £1,654,612.73  Paul Harding Laurence Potts  Vital Services Group Ltd, Vital Resources, Gresham Mill, South Hall Street, Salford M5 4TP   This contract was awarded on 30/01/12
South West  A35 Weymouth & Stinsford Roundabout Improvement   Road Improvement Sept 2010  April 2011  £2.1m   Alexis Wood Tony Ballinger   Birse Civils Ltd, Western Region, Stonehouse Business Park, Sperry Way, Stonehouse, Glos, GL10 3UT HA Ref: 13/5/2549 
East   A14 Orwell Bridge Phase 4 Bearing Replacement Replacement of Bearings   June 2010  Nov 2010  £1,100,855 Nicholas Royse  Alan Procter

 Jackson Civil Engineering Group Ltd

30 White House Road, Ipswich, Suffolk, IP1 5LT

 HA 13/1/846 (PE 796)
North East   A184 Whitemare Pool to Testos Roundabout  Full resurfacing of both East and Westbound carriageways  September 2011  October 2011  £676,893  Steve Bishop  Laura Watson Tarmac Ltd  
North East   A66 Cross Lanes to Rokeby Resurfacing  Removal and replacement of 85mm of pavement (small areas 300mm). The works will be carried out on night shifts only, with traffic signals and convoy working.  October 2011  October 2011  £761,064.00  Andrew Brown  Karen Evans  Tarmac Ltd.  
 South West

13/5/3765 

A38 Drumbridges to Goodstone resurfacing

 Resurfacing contract  October 2011  November 2011  £930,000  Alexis Wood  Jason Prichard  Hanson Contracting  

13/5/3765 

North East   
A19 Moor Farm to Killingworth Carriageway Resurfacing
 Resurfacing contract October 2011   November 2011  £906,330.00  Shaun Cullumbine  Dave Harvey  Tarmac Limited  
South West

13/5/3764

A30 Five Mile Hill

The Scheme will involve the stabilisation of 180m length of the embankment which supports the eastbound carriageway. The embankment varies from 13m to 20m in height with side slopes of approximately 1:2(v:h) and has been constructed from locally won shales of the Upper Carboniferous Crackington and Ashton Shale Formations  January 2012  April 2012 £1,031,418.41  Alexis Wood Jason Prichard  Birse Civils