Latest traffic information

Breadcrumb Navigation

You are here:

  1. »
  2. Home »
  3. Contact Us »
  4. Office Locations »
  5. Area Teams »
  6. Area 2 »
  7. The Severn Bridges »
  8. Picture Gallery

Website Navigation

Useful Links

Quick Links

Map Based Road Projects Finder - Feedback

We are currently piloting a new map based tool to help you find road projects. Please let us know what you think

The Project Control Framework

This framework sets out how we, together with the Department for Transport, manage and deliver major road improvement projects.

Picture Gallery

 

M48 Severn Bridge

The ferry service between Aust and Beachley ran from 1926 until the late 1960s

 

The ferry service between Aust and Beachley ran from 1926 until the late 1960s.

Severn King ferry

Severn King ferry

Spinning the Cables

spinning the cables

Wire unreeling equipment

wire unreeling equipment

The deck sections were floated into position, then lifted to their position supported by the main cable

The deck sections were floated into position, then lifted to their position supported by the main cable.

View of bridge deck prior to surfacing and finishings

View of bridge deck prior to surfacing and finishings.

Cable Wrapping Machine

Cable wrapping machine

The Severn Bridge as it is today

The Severn Bridge as it is today

M4 Second Severn Crossing

The construction site provided major facilities for pre-casting caisson, pier units and deck sections

The construction site provided major facilities for pre-casting caisson, pier units and deck sections

37 hollow caissons were pre-cast on shore, floated out on a barge at high water, positioned by a floating crane then filled with concrete

37 hollow caissons were pre-cast on shore, floated out on a barge at high water, positioned by a floating crane then filled with concrete

Caisson in position with floating crane in background at low tide

Caisson in position with floating crane in background at low tide

The 2km long viaducts on both sides of the bridge were built progressively from each shore using a purpose made gantry

The 2km long viaducts on both sides of the bridge were built progressively from each shore using a purpose made gantry

Launching gantry during viaduct construction

Launching gantry during viaduct construction

The main Shoots Bridge is a 947m long cable stayed structure with a composite deck supported by concrete pylons

The main Shoots Bridge is a 947m long cable stayed structure with a composite deck supported by concrete pylons

Each viaduct pier and main bridge pylon is supported on a precast concrete foundation, most of which are seated directly onto the rocky sea bed

each viaduct pier and main bridge pylon is supported on a precast concrete foundation, most of which are seated directly onto the rocky sea bed

Pre-cast deck unit being positioned using the launching girder

Second Severn Crossing as it is today