Latest traffic information

Breadcrumb Navigation

You are here:

  1. Home »
  2. Road Projects »
  3. How We Manage Our Roads »
  4. Area Teams »
  5. Area 2 »
  6. The Severn Bridges »
  7. Picture Gallery

Website Navigation

Useful Links

Feature

Better information for your journey

The National Traffic Control Centre collects real-time information on road conditions.

Quick Links

How We Manage Our Roads

In this section you can find out more about how we manage and maintain these roads and plan for the future

The Project Control Framework

On 1st April 2008 we launched the Project Control Framework. The Framework sets out how we, together with the Department for Transport, manage and deliver major improvement projects.

Traffic news on your desktop

Helpful ways to access the latest traffic information when you need it.

Picture Gallery

 

M48 Severn Bridge

The ferry service between Aust and Beachley ran from 1926 until the late 1960s

 

The ferry service between Aust and Beachley ran from 1926 until the late 1960s.

Severn King ferry

Severn King ferry

Spinning the Cables

spinning the cables

Wire unreeling equipment

wire unreeling equipment

The deck sections were floated into position, then lifted to their position supported by the main cable

The deck sections were floated into position, then lifted to their position supported by the main cable.

View of bridge deck prior to surfacing and finishings

View of bridge deck prior to surfacing and finishings.

Cable Wrapping Machine

Cable wrapping machine

The Severn Bridge as it is today

The Severn Bridge as it is today

M4 Second Severn Crossing

The construction site provided major facilities for pre-casting caisson, pier units and deck sections

The construction site provided major facilities for pre-casting caisson, pier units and deck sections

37 hollow caissons were pre-cast on shore, floated out on a barge at high water, positioned by a floating crane then filled with concrete

37 hollow caissons were pre-cast on shore, floated out on a barge at high water, positioned by a floating crane then filled with concrete

Caisson in position with floating crane in background at low tide

Caisson in position with floating crane in background at low tide

The 2km long viaducts on both sides of the bridge were built progressively from each shore using a purpose made gantry

The 2km long viaducts on both sides of the bridge were built progressively from each shore using a purpose made gantry

Launching gantry during viaduct construction

Launching gantry during viaduct construction

The main Shoots Bridge is a 947m long cable stayed structure with a composite deck supported by concrete pylons

The main Shoots Bridge is a 947m long cable stayed structure with a composite deck supported by concrete pylons

Each viaduct pier and main bridge pylon is supported on a precast concrete foundation, most of which are seated directly onto the rocky sea bed

each viaduct pier and main bridge pylon is supported on a precast concrete foundation, most of which are seated directly onto the rocky sea bed

Pre-cast deck unit being positioned using the launching girder

Second Severn Crossing as it is today

Second Severn Crossing as it is today