The Project Control Framework
This framework sets out how we, together with the Department for Transport, manage and deliver major road improvement projects.
DBFO projects - key dates and durations
| Project | Tender Issue Date | Tender Return Date | Invitation of BAFO Date | Return of BAFO Date | Preferred Bidder Date | Award Date |
|---|---|---|---|---|---|---|
| Tranche 1 | ||||||
| M1-A1 Lofthouse - Bramham (Kvaerner) | 09/01/95 | 12/06/95 | 29/09/95 | 06/10/95 | 15/10/95 | 26/03/96 |
| A419/A417 Swindon - Gloucester (RMG) | 09/01/95 | 30/05/95 | 29/09/95 | 06/10/95 | 16/10/95 | 08/02/96 |
| A1(M) Alconbury - Peterborough (RMG) | 09/01/95 | 22/05/95 | 29/09/95 | 06/10/95 | 16/10/95 | 08/02/96 |
| A69 Newcastle - Carlisle (Road Link) | 09/01/95 | 05/06/95 | 29/09/95 | 10/10/95 | 17/10/95 | 12/01/96 |
| Tranche 1A | ||||||
| M40 Denham - Warwick (UK Highways) | 14/06/95 | 30/10/95 | 26/03/96 | 03/04/96 | 24/04/96 | 08/10/96 |
| A168/A19 Dishford - Tyne Tunnel (Auto Link) | 14/06/95 | 06/11/95 | 12/04/96 | 29/04/96 | 16/05/96 | 14/10/96 |
| A30/A35 Exeter - Bere Regis (Connect) | 14/06/95 | 13/11/95 | 19/03/96 | 03/04/96 | 23/04/96 | 24/07/96 |
| A50 Stoke - Derby (Connect) | 14/06/95 | 23/10/95 | 23/01/96 | 12/02/96 | 27/02/96 | 20/05/96 |
| Post Tranche 2 | ||||||
| A1 Darrington to Dishforth | 27/03/01 | 27/09/01 | 02/05/02 | 29/05/02 | 23/09/02 | 13/02/03 |
| A249 Stockbury (M2) to Sheerness | 24/07/02 | 06/12/02 | 26/03/03 | 07/04/03 | 28/04/03 | 19/02/04 |
DBFO PROJECTS - KEY DATES & DURATION
View DBFO Projects - key dates & duration table (will open in new window).