Disabled Driver Questionnaire
We want to produce a driver information programme for our disabled customers. To help us produce the best possible guidance, please take a few minutes to fill in our questionnaire.
Better information for your journey
The National Traffic Control Centre collects real-time information on road conditions.
A3 Hindhead Improvement
The project will deliver quicker, more reliable journeys on a safer road.
Traffic news on your desktop
Helpful ways to access the latest traffic information when you need it.
M5 Jct 25 - 26 Resurfacing
M5 Jct 25 - 26 Resurfacing
- Status
- Completed
- Located in
- Area 2

- Scheme type
- Other

The Project
This combined safety and road improvement scheme, comprising of the re-surfacing of all three lanes on both the north and south bound carriageways of the M5 to include the hard shoulder, began on 18 April 2006 and was completed on 7 July 2006.
The project also involved the installation of safety barriers on the verges and the installation of concrete barrier to the central reserve, including necessary drainage repairs.
The travelling public will experience a quieter road surface and the upgraded central reserve barrier will prevent cross-over accidents, improving safety on this stretch of carriageway.
The work affected approximately 2 miles (3.4 k) of road between Taunton Deane Services and Wellington (Junction 26).