Latest
Home » Road Projects » Area 2 » Road Project
Contact us

by phone or email

Register for
email alerts

On information that's important to you

Feature

Disabled Driver Questionnaire

We want to produce a driver information programme for our disabled customers. To help us produce the best possible guidance, please take a few minutes to fill in our questionnaire.

Feature

Better information for your journey

The National Traffic Control Centre collects real-time information on road conditions.

Quick Links

The Project Control Framework

On 1st April 2008 we launched the Project Control Framework. The Framework sets out how we, together with the Department for Transport, manage and deliver major improvement projects.

Traffic news on your desktop

Helpful ways to access the latest traffic information when you need it.

A40 Huntley to Birdwood

A40 Huntley to Birdwood

Status
Completed
Located in
Area 2Map of the Agency's Operational Areas
Scheme type
OtherRoad Schemes Managed by the Highways Agency

The Project

This essential maintenance project involves reconstruction, resurfacing and drainage improvements to the main carriageway of the A40 between the villages of Huntley and Birdwood, west of Gloucester. The work is expected to start in January 2006 and is scheduled for completion by March 2006.

Following completion of the works, the improved drainage will increase safety for road users by reducing standing water on the carriageway. Residents of the area should also experience reduced road noise levels.

Traffic Management

The work will require traffic management through the area Monday to Friday, with total closure of the road on a weekend.

Local diversion routes will be in place during the closures and road users should allow extra journey time.

Update - Works Completed

The A40 Huntley to Birdwood maintenance project was completed on the 28th March 2006.