This month sees the opening of the A500 Basford Hough Shavington Bypass. About 80% of all traffic, including a large proportion of heavy goods vehicles, will be taken off the existing A500 bringing improved road safety for residents and users. The scheme complements local, regional and national planning policies by creating opportunities for new employment areas north of the bypass alongside the West Coast Main Line railway.
In the summer of 2001, work began to construct the dual carriageway between Meremoor Moss and Cheerbrook roundabout thereby easing congestion through the villages of Basford, Hough and Shavington.
Just over 22 months later and despite the start date being delayed several months due to the national Foot and Mouth outbreak, the road is now ready to open to motorists, some 4 months ahead of the planned completion date.
Major achievements during the building of the bypass include:
One of the major engineering achievements on the scheme was the successful completion of the London Crewe Railway Bridge. The bridge was constructed away from the railway line and launched across the tracks on Christmas Day and Boxing Day. The launch itself could only be undertaken during a 48 hour rail possession over Christmas 2001.
Included in the scheme, has been the construction of 3 overbridges to carry the three main side roads (Rope Lane, Crewe Road and Main Road) over the new bypass.
The bridges were built alongside the existing roads without the need for traffic management and once they were completed traffic was diverted onto the new bridges with minimum disruption.
The new bypass will have a variety of effects on the landscape along its route. Some vegetation has been lost, new structures introduced and some parts of the route are in cutting and others on embankment. All of these have had aneffect on the environment. A variety of landscape treatments have been adopted to blend the bypass into its surroundings.
These consist of:
There were a number of ecological challenges encountered in the construction of the bypass :
Select any part of map to access larger diagram
This map is reproduced from Ordnance Survey material by the Highways Agency Traffic and Operations Division with the permission of the Controller of Her Majesty's Stationery Office, © Crown Copyright. Unauthorised reproduction infringes Crown copyright and may lead to prosecution or civil proceedings.
Licence number 100018928.
The A500 Basford Hough Shavington Bypass site has received a Gold 2003 National Award from the Considerate Constructors Scheme.
The award was presented to Kevin Lucas - Project Manager, Mowlem in April at an award ceremony at Crewe Hall.
The award is in recognition of running a scheme that demonstrates that the Highways Agency and it's contractors put environmental sensitivity and public health and safety at the top of our agenda.
Liaison with the public started with a 2 day public exhibition held in the local village hall where key members of staff were present to answer questions and talk to people about concerns they may have had.
Regular meetings with the Headmaster at Shavington High School have taken place and a safety talk was given to all the pupils before construction work in that area started. Talks on site safety have also been given to several local scouts groups. The youngsters were shown a video outlining the dangers of playing on a construction site and given a talk on the safety aspects and construction of a major project like the A500 Basford Hough Shavington Bypass.
Several site visits have taken place. County, Borough and Parish Councillors visited the site and were given the opportunity to see at first hand how the project was being managed within the local community.
Regular newsletters have been distributed locally to keep people up to date with progress, forthcoming activities, environmental matters, people involved in the scheme and any other general news.
| Start date | 2nd April 2001 |
|---|---|
| Entry onto site | Mid June 2001 |
| Contractual completion date | End of September 2003 |
| Length of scheme | 7.5 kilometres |
| Scheme cost | £28 million |
| Standard | Dual 2 lane all purpose carriageway |
| Fencing | 19 kilometres |
| Excavation | 700,000 cubic metres |
| Drainage pipeline | 29 kilometres |
| Stone | 140,000 tonnes |
| Blacktop | 122,000 tonnes |
| Concrete | 7,700 cubic |
| Bridges | 8 |
| New ponds | 12 |
| Badger setts | 1 |
| Mammal tunnels | 7 |
| Trees planted | 19,500 |

Christmas day for us started at one minute past midnight when the bridge over the London - Crewe Railway started to move. In spite of torrential rain and howling winds, the Southern most span was in position by 6:30am. By dawn, the rain had blown itself out and blue sky and sunshine greeted our dayshift as we commenced preparation for launching the second half. A good number of local residents and staff members and their families turned up to watch and we extend our thanks to them for their support and their exemplary behaviour. The Northern span was finally in place by 3:00am on Boxing Day after a small hitch about two thirds of the way across. A significant achievement, congratulations to all involved.
The other area of main activity has been at Cheerbrook Roundabout where the roundabout is nearing completion and traffic is running around it. Use was made of the new Newcastle Road link whilst the roundabout was constructed.
Rope Lane is progressing well. We apologise for the great inconvenience caused to local Road users whilst this very complicated section of the work is undertaken and we ask you to bear with us for a few more weeks. Rope Lane Bridge was cast on 8th May.
On 27th March, Crewe Road Bridge Deck was cast using 805m3 of concrete, this has now gained its strength and the temporary support will shortly be dismantled and moved to Carters Green Farm Bridge.
We will soon complete Newcastle Road Diversion at the West End of the schemeand traffic will be transferred from the old road near the Horseshoe Pub. Whilst this is ongoing we again as for your forbearance.
Work continues on the side road crossings at Rope Lane, Crewe Road and Main Road, Weston, and we expect to have these nearing completion towards the end of the summer. Now that we have the bridge over the West Coast Main Line we can use it to move material from the East side to form embankments on the West side and start to shape the bypass along its full length. Given a favourable summer we expect to open the bypass several months early by spring 2003. We will shortly be starting work at the East End of the scheme at the A5020/A500 roundabout at Meremoor Moss. We have to enlarge the roundabout to allow for the connection of the bypass and some disruption to traffic will be inevitable. Please allow more time for your journey and drive safely through the roadwork's.

Our ecologists have been working hard to minimise the effects on wildlife throughout the site. You may have noticed the long lengths of polythene fencing at our site boundaries, which we use to trap and exclude Great Crested Newts, an important protected species. We have a licence to do this work from English Nature and we do not start full construction until the site is clear. We have created a number of new ponds near the bypass for the Newts and these should become havens for local wildlife. We have also successfully relocated a Badger sett from the line of the road and we are pleased to see that the Badger family is already extending their new home.

We would like to thank residents and commuters using the A51 during the weekend of 23rd and 24th March at Cheerbrook Roundabout, for their patience whilst major works were going on. We would also like to say a big thank you to residents of Crewe Road, Shavington, who again, were patient with us whilst we did a large concrete pour on the Crewe Road Bridge, opposite our site compound on 27th March. We apologise for any disruptions and inconvenience caused to local residents and people using Crewe Road during this time.
Last Issue: John Mowlem & Co PLC
This Issue: The Babtie Group (Design Consultant)
The Babtie Group, founded in 1895, is one of the UK's leading technical and management consultancies with offices throughout the UK as well as Europe and the Far East. Babtie has worked successfully with the Highways Agency and its predecessors for many years, establishing it's strong reputation by providing engineering excellence, together with innovation on over 20 Design & Build or DBFO (Design, Build, Fund, Operate) projects. Many projects, like the A500, demand close liaison with local residents and the public in general, an appreciation that Babtie has demonstrated through numerous public inquiries, public exhibitions etc.
The multi disciplinary nature of the company enables Babtie to provide expertise on a wide range of environmental issues such as noise, landscaping, ecology, archaeology, air quality and lighting. The A500 project has been able to benefit from these skills that are seen as essential to the successful delivery of major highway schemes. This has been amply demonstrated, for instance, by the company's approach to the diverse wildlife found on the site. Babtie's team on site is there to help Mowlem and to ensure that there is good communication between the designers and the builders.

Mole-M was devised with the intention of educating young children about the dangers associated with construction sites in a way which is entertaining and therefore easy for them to relate to.
Mole-M (a play on the John Mowlem & Company name) is a large furry mole who dresses in builder's attire and carries a shovel! He visits schools along with two human 'helpers' who introduce him and show pupils an interactive power-point presentation and a short video, both of which help highlight the dangers that can exist on construction sites.
For teachers wishing for Mole-M to visit their school please call the number below and we will arrange a day and time that is suitable for you and take a note of any specific needs you might have.
"Never play on construction sites,they are very dangerous!"

Mowlem have recently challenged various local companies, some associated to the A500 project and some not, to a series of 5 A Side football games. Currently Mowlem are topping the league, having won the majority of games so far this season. If anyone would like to challenge Mowlem to a game of 5 A Side, please do not hesitate to get in touch with Mr Roger Powell on the telephone number overleaf.
The Newcastle Link road, which ties into the existing A500, is now complete and open to traffic. However, landscaping and other minor works to allow access into adjacent farmland require completion. A Thirty Three Thousand volt cable passing underneath the line of the new main carriageway will be lowered this week. Similarly, BT will make connections to their new cables in Wybunbury Road. The old sections of the A500 and Wybunbury Road will then be removed allowing construction to continue with a clear run through to Rope Lane.
Crewe Road, Main Road and Rope Lane overbridges have all been constructed and soon will be carrying traffic over them, allowing new carriageway construction to continue underneath. Carters Green Farm and Mill Lane are also complete with Rope Farm Bridge scheduled for completion on 10th July, leaving Wybunbury Road cycle/footbridge the only structure to be completed. The majority of culverts and wildlife passes are also nearing completion.
The Western approach embankment to the Rail Bridge is under construction and this involves a fleet of articulated dump trucks moving earth from near Meremoor Moss, over the bridge.
There will be a series of overnight road closures of the A5020 commencing on Monday night 8th July 2002, to facilitate construction of the Meremoor Moss roundabout. Whilst this may cause some of the travelling public to use slightly longer diversioning routes, it should prevent the normal peak hour chaos from getting any worse. We trust you will all bear with us whilst we undertake this important section which ties the new road into the existing.
The translocation of protected species from the working areas of the project has been virtually completed. A running total of about 150 Great Crested Newts have been trapped and moved. The replacement habitats areas, including ponds that have been created, are flourishing now that the growing season is well under way and they are starting to look as though they have always been there. As progress with the actual surfacing of the road continues, wildlife passes or tunnels are being installed at appropriate locations to allow safe passage across the road for badgers etc. An unexpected visitor to the project has been the sand martin that has been looking to colonise the exposed faces of the sandy sub-soil uncovered temporarily by the earthworks. Bird scarers have been deployed, as well as sheeting, over areas at risk before works have been completed.
Whilst every care is taken to ensure that local residents from the Villages effected by the ongoing work are not unduly disturbed, there are inevitably times when sadly this cannot be achieved. Should anyone have any concerns, please feel free to call our site office and talk to a member of staff, who will endeavour to find an amicable solution to your problem. The address and phone number can be found on the back page of this Newsletter.
Last Issue: The Babtie Group (Design Consultant)
This Issue: Veryards (The Employers Agent)
VERYARDS Ltd was founded in 1959 as an independent professional partnership of civil and structural engineers. The firm quickly established a reputation for innovative and cost effective designs associated with commissions for national and local government departments, health authorities and private sector clients. In more recent times Veryards has been involved in design and build projects acting either as Employer's Agent or Contractor's Designer.
In 1988 the predecessor to the Highways Agency appointed the company to investigate alternative routes for a bypass of Basford, Hough and Shavington which forms part of a more general upgrading of the A51(T) strategic route between North Wales and Chester to the Midlands and beyond. Veryards, under the direction of the Highways Agency, has been responsible for dealing with all the normal statutory procedures including public consultation, preparation of the mainline and side roads Orders, public inquiry andcompulsory land purchase issues. Tender documents were prepared in accordance with the Department of Transport's Design and Construct form of procurement. Specialist sub-consultants have been employed to deal with environmental, ecological and street lighting matters.
During the construction phase of the project Veryards has responsibility for ensuring the requirements of the Highways Agency are fully met. They monitor the activities of the contractor and their designers and participate in meetings with interested parties. Communications with the local community affected by the scheme also plays an important part of their work.
The Considerate Constructors Scheme is a voluntary Code of Practice, driven by the Industry, which seeks to:
John Mowlem & Company PLC are registered with the Considerate Constructor Scheme and upon a recent site inspection at the A500 Basford Hough Shavington Bypass project, we are proud to have scored a total 39½ out of 40. We feel that participating in the scheme demonstrates that we put environmental sensitivity and public health and safety at the top of our agenda.
Considerate Construction provides high standards of site cleanliness and tidiness, better site housekeeping and traffic management, less dust and noise, environmental friendliness and greater community involvement, which results in improved understanding and respect from residents and others in the community, and fewer complaints. A clean tidy, organised and well managed construction project is also safer for both those operating around it and those working on site who enjoy better working conditions and are as a result a more productive workforce. Being a Considerate Constructor is consequently a 'win win' situation for all those involved.
Considerate - Environment - Cleanliness - Good Neighbours - Respectful - Safe - Responsible - Accountable
Should you have any queries or concerns please contact:
Gaynor Mellor, A500 Project Office, Crewe Road, Shavington, Crewe, Cheshire CW2 5AH Tel: 01270 666195
Mowlem have agreed to sponsor a youth league from the Crewe Alex Soccer Academy for the forthcoming season.
Currently the Mowlem 5 a side team remain unbeaten and would welcome challenges from local business's/teams.
If anyone would like to challenge Mowlem to a game of 5 a side please contact Kevin Lucas, Project Manager on the number overleaf.
The A500 Basford, Hough, Shavington Bypass officially opened on Thursday 22nd May 2003, providing relief from traffic for the villages of Shavington and Hough in Cheshire. The scheme consists of an approximately 7.5 km long new section of dual carriageway road accessed from roundabouts at either end. There is an intermediate access on Crewe Road just north of Shavington village, and another (the easternmost access, as shown on the map) due to open in the future near to Mill Lane just north of Weston.
The layout of the scheme is shown in Figure 1.

The objectives of the scheme were defined in the Scheme Appraisal Summary Table (AST) and can be summarised as follows:
In order to assess whether these objectives have been achieved, traffic flow and journey time data for the bypassed section of the original A500 were collected immediately prior to and after scheme opening and 'after' data for the bypass itself was also collected in order to monitor the effects of the new scheme.
In addition, traffic data from existing Highways Agency permanent count sites and from Cheshire County Council temporary sites was obtained in order to evaluate the effects of the opening of the A500 Basford, Hough, Shavington Bypass on strategic traffic routing patterns in the area.
A comparison of the 'Before' and 'After' traffic volumes is shown in Figure 0.2.

In the weeks following opening, the three main traffic effects of the bypass were:



At other locations on the old A500 the pattern is similar:
Table 3.1 - Journey Times for New Route
| Direction | Period | Route Used | Time saved using new A500 | Old A500 (After) | Time Saved using old A500 | |
|---|---|---|---|---|---|---|
| Old A500 | New A500 | |||||
| (Before) | (After) | |||||
| Eastbound | AM | 10:29 | 08:10 | 02:19 | 09:08 | 01:21 |
| INTER | 10:31 | 06:43 | 03:48 | 08:51 | 02:40 | |
| PM | 10:50 | 07:05 | 03:45 | 09:45 | 01:05 | |
| Westbound | AM | 10:17 | 06:42 | 03:35 | 09:33 | 00:44 |
| INTER | 10:49 | 06:37 | 04:12 | 10:10 | 00:39 | |
| PM | 10:39 | 06:57 | 03:42 | 08:45 | 01:54 | |
Table 3.2 - Journey Times for Northern Route
| Direction | Period | Route Used | Time Saved using existing A5020/A534 | |
|---|---|---|---|---|
| A5020/A534 (Before) | A5020/A534 (After) | |||
| Eastbound | AM | 26:16 | 13:49 | 12:27 |
| INTER | 14:17 | 14:03 | 0:14 | |
| PM | 20:40 | 23:10 | -2:30 | |
| Westbound | AM | 17:04 | 15:27 | 1:37 |
| INTER | 13:37 | 13:15 | 0:22 | |
| PM | 26:22 | 18:21 | 8:01 | |
Table 3.3 - Journey Times for Southern Route
| Direction | Period | Route Used | Time Saved using existing A500 | |
|---|---|---|---|---|
| Old A500 (Before) | Old A500 (After) | |||
| Eastbound | AM | 10:29 | 09:08 | 1:21 |
| INTER | 10:31 | 08:51 | 1:40 | |
| PM | 10:50 | 09:45 | 1:05 | |
| Westbound | AM | 10:17 | 09:33 | 0:44 |
| INTER | 10:49 | 10:10 | 0:39 | |
| PM | 10:39 | 08:45 | 1:54 | |
Table 3.4 - Journey Times for Cross Route
| Direction | Period | Route Used | Time Saved using Crewe Rd | |
|---|---|---|---|---|
| Crewe Rd (Before) | Crewe Rd (After) | |||
| Northbound | AM | 08:07 | 08:06 | 0:01 |
| INTER | 07:30 | 07:44 | -0:14 | |
| PM | 10:45 | 07:02 | 3:43 | |
| Southbound | AM | 05:53 | 06:49 | -0:56 |
| INTER | 08:06 | 06:09 | 1:57 | |
| PM | 06:38 | 07:21 | -0:43 | |

Table 3.5 - Comparison of Journey Speeds (KPH)
| Direction | Period | Before | After | |
|---|---|---|---|---|
| A500 Av. Speed (kph) | Old A500 Av. Speed (kph) | New A500 Av. Speed (kph) | ||
| Eastbound | AM | 51 | 59 | 67 |
| INTER | 51 | 60 | 68 | |
| PM | 50 | 55 | 65 | |
| Westbound | AM | 52 | 56 | 55 |
| INTER | 50 | 53 | 70 | |
| PM | 50 | 61 | 64 | |
Table 3.6 - Variation in Journey Times on Cross Route
| Direction | Period | Before | After |
|---|---|---|---|
| Northbound | AM | 21% | 9% |
| INTER | 27% | 9% | |
| PM | 81% | 13% | |
| Southbound | AM | 22% | 20% |
| INTER | 24% | 10% | |
| PM | 33% | 20% |
Despite the wide variation, the opening of the new route appears not to have had a detrimental effect on the B5071 between Shavington village and Crewe.