1.1 The A43 (T) Silverstone and Whitfield Turn to Brackley Hatch (Syresham bypass) improvement schemes officially opened on the 18th September 2002, providing an improved route for through traffic using the A43 between the M40 and M1 and for regional movements between Brackley and Towcester, Northamptonshire. The location of the improvements in the wider regional context is illustrated in Figure 1.1 below. The opening of these combined schemes provided a continuous dual carriageway between the M40 and A5. They comprise two sections of new dual carriageway, bypassing the villages of Silverstone and Syresham, as well as widening of the remaining single carriageway sections.
1.2 Also shown on Figure 1.1 is the M40 to B4031 Improvement scheme undertaken by the Highways Agency, which was completed in February 2002. As this Report focuses on the effects of the two more recent improvement schemes, the traffic volumes for the ‘Before’ situation have been taken post February 2002, and thus include the effects of the M40-B4031 scheme.
Figure 1.1 – A43 improvement schemes
1.3 Figure 1.2 below shows the completed scheme in more detail.
Figure 1.2 – Silverstone and Syresham bypass
1.4 In order to assess the immediate responses to the new scheme, ‘Before’ and ‘After’ traffic volume data on the A43 and other competing routes was collected immediately prior to and after opening in September 2002 to monitor the effects of the new scheme.
1.5 In addition, traffic data from surveys on County roads from Northamptonshire County Council and existing Highways Agency permanent count sites was obtained to evaluate the effects of the opening of the A43 (T) Silverstone and Syresham bypasses on strategic traffic routeing patterns in the area and the effects of this immediate response to the improvements was reported in the Traffic Impact Study Report.
1.6 The A43 improvements are made up of two named schemes within the Highways Agency’s Road Programme called the Targeted Programme of Improvements (TPI), namely:
1.7 These schemes were implemented to address the following problems, which are listed within the scheme Appraisal Summary Tables (AST). These problems were:
1.8 This report represents the ‘One-Year After’ report for the A43 improvement schemes. This report has been prepared as part of the Post Opening Project Evaluation (POPE) Commission and builds on the Traffic Impact Study (TIS) report prepared for the Highways Agency in December 2002.
1.9 This report will set out a number of assessments, namely:
1.10 This report specifically considers the re-evaluation of the predicted benefits for the A43 improvements including the Silverstone and Syresham bypasses. The three main elements involved are:
1.11 Following this introduction the report has been divided into five further sections as follows:
1.12 It should be noted, that the ‘One-Year After’ report is primarily focused on the evaluation of Economy and Safety sub-objectives of the GOMMMS Appraisal. Environmental evaluation has not been carried out at this stage, but will form part of the ‘5-Year After’ evaluation.
2.1 This One Year ‘After’ Report for the A43 (T), M40 to A5 Dualling, includes the following surveys:
2.2 The details of the ‘Before’ and ‘After’ surveys (with OSGR’s for site locations) are described below.
2.3 Atkins undertook automatic traffic count (ATC) surveys in September 2002 and September 2003 at the following six locations, as illustrated in Figure 2.1:
2.4 Traffic data from surveys undertaken by Atkins on behalf of Northamptonshire County Council to monitor the effects of the scheme opening on other routes in Northamptonshire and data from permanent Highways Agency count sites was also obtained to ensure a comprehensive evaluation of any strategic traffic routeing changes in Northamptonshire.
2.5 The County sites are as follows (and illustrated in Figure 2.1):
2.6 Traffic data was also obtained from Highways Agency permanent count sites on trunk roads (as shown in Figure 2.1), namely;
Figure 2.1 – Location of Traffic Count Sites
2.7 Journey time surveys were undertaken on the A43 (T) between the junction 10 of the M40 and A5 at Towcester. The surveys covered the full A43 (T) M40 - A5 Dualling Scheme, which includes the M40 to B4031 (A421) improvement (dualling of existing single carriageway road) which was completed in February 2002. The survey route, comprising five timing points, is depicted in Figure 2.2.
2.8 ‘Before’ journey time surveys previously undertaken in September 2002 were used for comparison with surveys carried out post scheme opening. Survey periods were the morning (07:30 – 09:00) and evening (16:30 - 18:00) peaks as well as an interpeak period (10:00 -11:30).
Figure 2.2 – Journey Time Survey Route from M40 to A5
2.9 Figure 2.3 below shows the changes in daily traffic volumes on the A43 and other roads in the area. All ‘Before’ traffic volumes have been factored up to reflect September 2003 traffic levels to ensure the conclusions drawn take into account seasonality and normal traffic growth.
Figure 2.3 –Traffic Volume Changes around Silverstone and Syresham
2.10 The main points to note for traffic volume changes on the A43 are:
2.11 These increases on the A43 are explained by traffic changes elsewhere, namely:
2.12 Figure 2.4 below shows the monthly variation in traffic, on the A43 at Brackley from January 2002 to December 2003. The timing of the A43 improvement schemes is also shown and clearly the step change in traffic volumes after scheme opening is immediately apparent. Comparing January-August 2002 with January-August 2003, there is an increase of 35% in traffic volumes over the two periods.
Figure 2.4 – Monthly Variation in Traffic Flows on the A43 at Brackley
2.13 This section of A43 is obviously adjacent to the Silverstone Motor Racing Circuit. As traffic volumes are continually monitored in this area, Annex A contains a section on traffic volumes on the A43 during the F1 weekend and compares these traffic volumes with non-race weeks to identify changes and trends.
2.14 It is also important to note that the scheme has not only been beneficial for the F1 weekend but for other events held at the circuit including Superbikes and Grand Touring cars. The Silverstone Motor Racing Circuit is used for events on most weekends of the summer, and the improvement has facilitated easier access to these events.
2.15 Journey Time surveys were undertaken on the A43 (T) between Junction 10 of the M40 and A5 at Towcester for both the ‘before’ situation and after the A43 was improved.
2.16 The surveys covered the full A43 (T) M40 - A5 Dualling Scheme, which includes the M40 to B4031/A421 improvement (dualling of existing single carriageway road) south of Brackley, which was completed in February 2002. Survey periods were the morning (07:30 – 09:00) and evening (16:30 - 18:00) peaks as well as an inter-peak period (10:00 -11:30).
2.17 The ‘before’ and ‘after’ survey periods were September 2002 and September 2003 respectively, and thus the time savings shown reflect the completion of the Silverstone and Syresham improvements on this section of A43. The survey route is depicted in Figure 2.2.
2.18 The Journey Time Survey results are shown in Table 2.1 below.
| Direction | Period | Journey Time (Mins) | |||
|---|---|---|---|---|---|
| Before (Sept 02) | After (Sept 02) | 1 Year After (Sept 03) | Saving (Before & 1- year after) | ||
| Northbound | AM | 26:18 | 18:38 | 18:55 | 07:23 |
| Inter | 25:25 | 17:44 | 18:55 | 06:30 | |
| PM | 28:53 | 20:57 | 19:42 | 09:11 | |
| Southbound | AM | 29:07 | 18:37 | 19:01 | 10:06 |
| Inter | 26:25 | 17:44 | 18:53 | 07:32 | |
| PM | 28:45 | 19:27 | 19:25 | 09:20 | |
2.19 From the Journey Time data it is suggested that initial time savings in the weeks after opening were up to 10 minutes, and these levels of time savings have been sustained one-year after opening.
2.20 There is also a significant improvement in the variability of the Journey Times. Before the two schemes opened, there was around a 3 minute time difference between the AM and Inter peak in the southbound direction, but the ‘after’ times are very consistent between all time periods and for both directions, thus the journey time reliability is very much improved.
2.21 Table 2.2 below compares the Journey Speeds ‘Before’, ‘After’ and ‘One Year After’ scheme opening. Average speeds on the new A43 bypass are up to 20 - 27 kph faster a year after scheme opening, and journey speeds are very consistent at around 86 kph, thus confirming the improvement in journey reliability; and implying that free flow is being achieved in all time periods and in both directions.
| Direction | Period | Journey Speeds (kph) | |||
|---|---|---|---|---|---|
| Before (Sept 02) | After (Sept 02) | 1 Year After (Sept 03) | Saving (Before & 1- year after) | ||
| Northbound | AM | 62 | 87 | 86 | 24 |
| Inter | 64 | 92 | 86 | 22 | |
| PM | 56 | 78 | 83 | 27 | |
| Southbound | AM | 56 | 87 | 86 | 20 |
| Inter | 62 | 92 | 86 | 24 | |
| PM | 57 | 84 | 84 | 27 | |
3.1 As part of this ‘One-Year’ After Study, the Report is also assessing the predicted level of economic benefits. This section assesses the level of economic benefits predicted for each of the two A43 schemes and compares these predictions with actual benefits accrued when considering actual traffic volume changes and actual journey time benefits.
3.2 Two evaluations have been undertaken, one for the 8km Silverstone section, and one for the 4.6km Whitfield Turn to Brackley Hatch (Syresham) section. These have been evaluated separately as the original appraisals were also undertaken separately.
3.3 The approach that we have taken is termed the Post Opening Project Evaluation (POPE) methodology. The basis of the POPE methodology is that through previous COBA evaluations undertaken it has been identified that the majority of benefits are derived primarily from two areas:
3.4 As such, link transit time, (which is represented by traffic volumes multiplied by journey times) and the number of accidents can be collected before and after scheme opening and the difference between these observed values can be compared to the difference shown in time and accidents for the same links shown in the OPR COBA’s. The premise of the POPE methodology is that the change in the observed flows, times and accidents can be directly associated to the economic benefits predicted for this scheme.
3.5 The following section outlines this approach in more detail.
3.6 To calculate link transit time or vehicle hour benefits, the COBA deck from OPR must be available, and the following changes implemented so that sensible and like-for-like comparisons can be made:
3.7 In considering the changes between the OPR COBA and the observed vehicle hour benefits, we are limited by the availability of data. Only peak hour and off peak hour journey times are available for the key links before and after opening, even though count data has been collated for the whole 24 hour period.
3.8 This means that only the bypass and bypassed links (where data IS available) are considered in the POPE assessment, and thus the change in vehicle hours can be compared with the change in link transit time for the same links in the OPR COBA.
3.9 This test assumes that flow data, on key links, is available by hour for a 24 hour period and journey time data is only available for the peak and off peaks.
3.10 This means that expansion factors from peak hour to peak period and off peak period to all other hours have been calculated from the Do Minimum observed flow data. This has then been used to factor up the outturn data to a total average day.
3.11 Tables 3.1 and 3.2 below show the differences between the vehicle hours before and after opening of the bypasses (observed traffic volumes multiplied by times) and the differences between flow x times for the same links in the OPR COBA.
| Total Vehicle-Hours per year | |||
|---|---|---|---|
| Low Growth | High Growth | ||
| OPR COBA | DM | 740400 | 880826 |
| DS | 635441 | 733533 | |
| Difference | 104959 | 147293 | |
| Observed | ‘Before' | 1066336 | 1066336 |
| ‘After' | 858976 | 858976 | |
| Difference | 207360 | 207360 | |
| Total Vehicle-Hours per year | |||
|---|---|---|---|
| Low Growth | High Growth | ||
| OPR COBA | DM | 437693 | 499036 |
| DS | 344270 | 385523 | |
| Difference | 93423 | 113513 | |
| Observed | ‘Before' | 716811 | 716811 |
| ‘After' | 521456 | 521456 | |
| Difference | 195355 | 195355 | |
3.12 Table 3.1 shows that the saving in observed vehicle hours for the Silverstone schemes is 207,000 hours over the year. For the same links and scheme year, the Low Growth prediction was 105,000. The OPR COBA assessment showed that the Link Transit Time benefits for this scheme were £12.910 million.
3.13 This means that 105,000 vehicle hour saving correlates to £12.9 million of benefits, and using the same relationship between vehicle hours saved and economic benefit, the observed 207,000 hours saved correlates to £25.5 million benefits. Thus, the outturn benefits are estimated to be almost double what was predicted.
| Difference in VehicleHours for Silverstone | ||||
|---|---|---|---|---|
| OPR stage | Actual | |||
| Difference | Link Transit Time Benefits | Difference | Predicted Benefit | |
| Low Growth | 104,959 | £12.910m | 207,360 | £25.505m |
| High Growth | 147,293 | £25.319m | 207,360 | £35.644m |
| Difference in VehicleHours for Silverstone | ||||
|---|---|---|---|---|
| OPR stage | Actual | |||
| Difference | Link Transit Time Benefits | Difference | Predicted Benefit | |
| Low Growth | 93,423 | £4.268m | 195,355 | £8.925m |
| High Growth | 113,513 | £8.003m | 195,355 | £13.773m |
3.14 Tables 3.3 and 3.4 summarise the POPE estimate of benefits for both Low and High Growth for the Silverstone and Syresham Improvement schemes, and shows:
3.15 It was normal at the time of the OPR assessment for Low and High Growth to be weighted to create an average cost, by utilising 60% of the Low Growth result, and 40% of the High Growth Result. We have retained this assumption when considering weighted growth in this report. Thus, the POPE comparison suggests:
| Predicted Benefits £m |
POPE Outturn Benefits £m |
% Increase £m | |
|---|---|---|---|
| Silverstone Section | 17.9 | 29.6 | 65% |
| Syresham Section | 5.8 | 10.9 | 85% |
3.16 Thus, the actual time benefits for the Silverstone scheme are around 65% higher than those originally forecast, and around 85% higher than forecast for the Syresham section.
3.17 Table 3.6 below shows the difference between the actual number of accidents before and after opening of both bypasses and the difference between the number of accidents predicted by COBA.
| Total Number of accidents per year | |||
|---|---|---|---|
| Low Growth | High Growth | ||
| OPR COBA | DM | 49 | 55 |
| DS | 19 | 21 | |
| Saving | 30 | 34 | |
| (reduction) | (61%) | (62%) | |
| Actual | ‘Before’ | 46 | 46 |
| ‘After’ | 28 | 28 | |
| Saving | 18 | 18 | |
| (reduction) | (39%) | (39%) | |
3.18 COBA has predicted a saving of 30 accidents, for low growth, whereas the actual saving, along the same links and scheme year, is only 18 accidents.
3.19 The OPR COBA assessment showed that the Accident Benefits were £15.082 million, at low growth. This means that 30 accidents saved correlates to £15.1 million of benefits, and using the same relationship between accidents saved and economic benefit, the observed saving of 18 accidents equates to £9 million benefits. Thus, the outturn benefits are estimated to be only 60% of what was predicted.
| Accident saving at Silverstone and Syresham | ||||
|---|---|---|---|---|
| OPR stage | Actual | |||
| Difference | Accident Benefit | Difference | Predicted Benefit | |
| Low Growth | 30 | £15.082m | 18 | £9.049m |
| High Growth | 34 | £22.561m | 18 | £11.944m |
3.20 Table 3.7 above summarises the POPE estimate of benefits for both Low and High Growth for the Silverstone and Syresham Improvement schemes, and shows:
3.21 The weighted benefit is 44% lower than that was originally forecast, as shown in Table 3.8 below.
| &OPR Predicted Benefits £m |
POPE Outturn Benefits £m |
% decrease £m | |
|---|---|---|---|
| Improvement Scheme | 18.1 | 10.2 | 44% |
3.22 These results suggest that the POPE methodology may be a robust way of evaluating link transit time benefits, particularly when most of the key links have all been counted and journey times have been undertaken.
3.23 The POPE methodology for accidents should be treated with caution, as it is normal for changes in accidents to be assessed over 3-5 years. Therefore, conclusions can only be considered as indicative when they are derived from only one year’s data.
3.24 Thus, the POPE methodology will continue to be used on other schemes in order to provide a larger sample to verify POPE as an evaluation tool.
4.1 Economic benefits of a scheme have been traditionally assessed using the Government’s COBA (Cost Benefit Analysis) program, which considers changes in:
4.2 This section presents a comparison of predicted benefits as calculated by COBA and an assessment of what those benefits would be if the outturn traffic volumes and journey time savings were known at the time.
4.3 The original Order Publication Report (OPR) COBA appraisal provided the level of benefits that were predicted for these schemes at Public Inquiry. These COBA assessments have been obtained from Government records, and then three additional assessments have been undertaken to provide a re-evaluation of scheme benefits. These were:
4.4 Figures 4.1 and 4.2 overleaf show the simple COBA network that was used in the appraisal of these schemes, and Tables 4.1 - 4.4 show the Low and High growth COBA results for each of these stages for each of the two A43 improvement schemes.
Figure 4.1 - COBA network for Silverstone
4.5 Tables 4.1 and 4.2 show the re-assessment of economic benefits for the A43 Silverstone improvement, where all costs and benefits are shown in 1988 prices discounted to 1988 (at 6%).
| Silverstone (£000’S) | ||||
|---|---|---|---|---|
| LOW GROWTH | 0. COBA Replication | 1. Updating Economic Parameters | ||
| COBA ITEM | OPR (printout) | Replication | Outturn Count data included | Count and Journey Times included |
| Link Transit Time | 12,910 | 12,915 | 24,423 | 22,759 |
| Operating Costs - Fuel | -1,500 | -1,500 | -2,097 | -2,100 |
| Operating Costs - Other | -797 | -794 | -793 | -831 |
| Junction Delay | 565 | 565 | 1,622 | 1,382 |
| Accidents Link | 9,921 | 9,921 | 13,548 | 13,548 |
| Accidents Junction | 775 | 775 | 871 | 871 |
| Construction Delay | 0 | 0 | 0 | 0 |
| Main Exp Saving | -295 | -295 | -295 | -295 |
| PVB (£) | 21,579 | 21,587 | 37,279 | 35,334 |
| Silverstone (£000’S) | ||||
|---|---|---|---|---|
| LOW GROWTH | 0. COBA Replication | 1. Updating Economic Parameters | ||
| COBA ITEM | OPR (printout) | Replication | Outturn Count data included | Count and Journey Times included |
| Link Transit Time | 25,319 | 25,326 | 35,288 | 33,223 |
| Operating Costs - Fuel | -1,079 | -1,079 | -1,252 | -1,258 |
| Operating Costs - Other | -878 | -875 | -770 | -810 |
| Junction Delay | 1,464 | 1,464 | 1713 | 1,509 |
| Accidents Link | 14,712 | 14,711 | 17,500 | 17,500 |
| Accidents Junction | 1,054 | 1,055 | 1,315 | 1,315 |
| Construction Delay | 0 | 0 | 0 | 0 |
| Main Exp Saving | -295 | -295 | -295 | -295 |
| PVB (£) | 40,297 | 40,307 | 53,499 | 51,184 |
4.6 Table 4.1 shows that for the A43 Silverstone section, the predicted economic benefits of this scheme at the time of the Public Inquiry were estimated to be £21.6m for a Low Growth assumption and £40.3m for High Growth. We have replicated this assessment, as shown in column 2 of Tables 4.1 and 4.2.
4.7 When the actual traffic volumes are inserted into the assessment, the benefits increase substantially to around £37m for Low Growth (a 70% increase) and £53.5m for High Growth, which represents a 33% increase. This column therefore reflects the COBA run that would have resulted if the COBA had been done at the OPR stage, but the actual 2003 flows were somehow given to the consultant at that time.
4.8 The inclusion of refined journey time calculations to reflect actual journey times observed after opening does not change the benefits significantly, suggesting that the COBA is calculating times adequately in its default settings, and also confirms that the inclusion of outturn traffic volumes into the Do Minimum (DM) scenario do not result in significantly increased delays and that the DM times remain robust.
4.9 Table 4.3 and 4.4 below show the results of the re-evaluation of economic benefits for the A43 Syresham section.
| Syresham (£000’S) | ||||
|---|---|---|---|---|
| LOW GROWTH | 0. COBA Replication | 1. Updating Economic Parameters | ||
| COBA ITEM | OPR (printout) | Replication | Outturn Count data included | Count and Journey Times included |
| Link Transit Time | 4,268 | 4,268 | 9,226 | 9,310 |
| Operating Costs - Fuel | -360 | -361 | -700 | -708 |
| Operating Costs - Other | 358 | 357 | 573 | 568 |
| Junction Delay | -176 | -176 | 429 | 375 |
| Accidents Link | 3,994 | 3,993 | 6,067 | 6,068 |
| Accidents Junction | 392 | 392 | 359 | 359 |
| Construction Delay | 0 | 0 | 0 | 0 |
| Main Exp Saving | -129 | -129 | -129 | -129 |
| PVB (£) | 8,347 | 8,344 | 15,825 | 15,843 |
| Syresham (£000’S) | ||||
|---|---|---|---|---|
| LOW GROWTH | 0. COBA Replication | 1. Updating Economic Parameters | ||
| COBA ITEM | OPR (printout) | Replication | Outturn Count data included | Count and Journey Times included |
| Link Transit Time | 8,003 | 8,003 | 14,420 | 14,598 |
| Operating Costs - Fuel | -283 | -284 | -442 | -448 |
| Operating Costs - Other | 426 | 424 | 628 | 622 |
| Junction Delay | -210 | -209 | 600 | 517 |
| Accidents Link | 6,210 | 6,210 | 8,437 | 8,437 |
| Accidents Junction | 585 | 585 | 551 | 551 |
| Construction Delay | 0 | 0 | 0 | 0 |
| Main Exp Saving | -129 | -129 | -129 | -129 |
| PVB (£) | 14,602 | 14,600 | 24,065 | 24,148 |
4.10 Table 4.3 and 4.4 show that for the A43 Syresham section, the predicted economic benefits of this scheme were estimated to be £8.3m and £14.6m for Low and High Growth respectively. These original predictions have been replicated.
4.11 When the actual traffic volumes are used, the benefits increase substantially to around £16m for Low Growth (a 90% increase) and £24m for High Growth, which represents a 65% increase.
4.12 The inclusion of actual journey times observed after opening also do not change the benefits significantly.
4.13 Clearly however, Tables 4.1 - 4.4 show that the inclusion of actual traffic volumes and journey times significantly increases the level of economic benefits accruing for these related improvements. The most important factor in this increase is the level of traffic growth in the corridor, which has been larger than predicted, thus the expected time savings are accruing to a greater level of traffic volumes.
4.14 For example, the predicted traffic volumes on the A43 Bypass at Silverstone and Syresham in 2003 were 21,200 and 19,700 vpd respectively, whereas the actual traffic volumes at these locations were 33,900 and 34,800 vpd respectively. This is a 60% increase at Silverstone and 77% increase at Syresham.
4.15 Table 4.5 below shows the weighted COBA and Outturn results, obtained from 60% of the Low Growth result and 40% of the High Growth Result. This shows that the outturn Silverstone benefits are 43% higher than predicted and for the Syresham section, the benefits are 77% higher than predicted.
| Predicted Benefits £m |
Outturn Benefits £m |
% Increase £m | |
|---|---|---|---|
| Silverstone Section | 29.1 | 41.7 | 43% |
| Syresham Section | 10.8 | 19.2 | 77% |
4.16 The previous section showed that additional traffic volumes have been attracted into the A43 corridor from other routes, notably the M40, A361 and A422. The COBA networks used for the assessment of benefits did not include these other routes and therefore the predictions were based on a straight switch of traffic from the old road to the new road. This approach clearly underestimated the level of benefits predicted for these schemes. Two alternatives could have been modelled, namely
4.17 Tables 4.1 – 4.4 show that the total predicted accident benefit of both of the A43 Improvement schemes was estimated to be £15.082m for low growth and £22.561m for high growth. The accident benefits for the two sections have been summed to give an overall benefit, using 60% of low growth and 40% of high growth.
4.18 The inclusion of outturn traffic volumes significantly increases the level of accident benefits, as with the case with the link transit benefits. Again, for both schemes in total, accident benefits of £20.846m for low growth and £27.803m for high growth are shown.
| Predicted Benefits £m |
Outturn Benefits £m |
% Increase £m | |
|---|---|---|---|
| Improvement Scheme | 18.1 | 23.6 | 30% |
4.19 Table 4.6 above shows that the weighted outturn benefits are 30% higher than that predicted.
4.20 The previous section showed that actual savings in vehicles hours could be used a proxy for the change in link transit and accident benefits, whereas this section has undertaken a good deal of COBA manipulation to insert actual traffic volumes and times into the original OPR COBA, to evaluate the level of benefits that would accrue given the COBA methodology, but using actual flows and times.
4.21 Tables 4.7 and 4.8 show the comparison, for link transit benefits, between the POPE and COBA methodologies for the Silverstone and Syresham schemes respectively. Table 4.9 overleaf shows the same comparison for the accident benefits.
| Predicted Link Transit Benefits £m |
Outturn Link Transit Benefits £m |
% Increase £m | |
|---|---|---|---|
| POPE Methodology | 17.9 | 29.6 | 65% |
| COBA Methodology | 17.9 | 26.9 | 51% |
| Predicted Link Transit Benefits £m |
Outturn Link Transit Benefits £m |
% Increase £m | |
|---|---|---|---|
| POPE Methodology | 5.8 | 10.9 | 85% |
| COBA Methodology | 5.8 | 11.4 | 98% |
| OPR Predicted Benefits £m |
Outturn Accident Benefits £m |
% Increase £m | |
|---|---|---|---|
| POPE Methodology | 18.1 | 10.2 | -44% |
| COBA Methodology | 18.1 | 23.6 | 31% |
4.22 This comparison shows that the POPE and COBA methodologies produce similar levels of outturn benefits for the link transit benefits, and thus POPE is potentially a robust way of establishing outturn economic benefits without recourse to timeconsuming COBA manipulations. This is not the case when evaluating accident benefits. Clearly, the two methodologies show very different results, but this confirms the need for at least 3 years worth of accident data, post scheme opening, and not one years worth, as was used here.
4.23 As well as re-assessing the level of benefits accrued by the two A43 schemes, we have also undertaken a review of predicted and actual costs. Tables 4.10 and 4.11 overleaf present the predicted costs calculated before opening as part of the justification of the scheme for both the Silverstone and Syresham improvements, as well as the actual costs converted to the same price base so that direct comparisons can be made between them.
| Silverstone | Syresham | |||
|---|---|---|---|---|
| predicted £m |
outturn £m |
predicted £m |
outturn £m | |
| Construction | 7.936 | 5.756 | 4.058 | 4.317 |
| Land | 0.250 | 0.233 | 0.206 | 0.233 |
| Preparation | 0.491 | 0.204 | 0.256 | 0.154 |
| Supervision | 0.246 | 0.509 | 0.128 | 0.385 |
| Total | 8.923 | 6.702 | 4.648 | 5.089 |
| Silverstone | Syresham | |||
|---|---|---|---|---|
| predicted £m |
outturn £m |
predicted £m |
outturn £m | |
| Construction | 30.685 | 22.256 | 15.691 | 16.692 |
| Land | 0.967 | 0.901 | 0.797 | 0.901 |
| Preparation | 1.899 | 0.788 | 0.990 | 0.595 |
| Supervision | 0.951 | 1.969 | 0.495 | 1.488 |
| Total | 34.502 | 25.914 | 17.972 | 19.677 |
4.24 The comparison of OPR and Outturn costs show:
4.25 Outturn costs shown are exclusive of two unique events, namely:
4.26 Together, these additional costs amounted to £25.6 million, but have been excluded from the above assessment, as clearly, these could not have been foresaw in the predictions of construction costs for these schemes.
5.1 In order to evaluate fully the effects of the opening of the two A43 improvement schemes, we have undertaken a review of the Appraisal Summary Table (AST) prepared for each of the improvements. Tables 5.1 and 5.2 present the AST’s for Silverstone and Syresham bypasses respectively.
5.2 These AST’s summarise the predicted impacts of the two schemes across a range of different sub-objectives. The sub-objectives considered within an AST are:
5.3 The main points to note from the Silverstone and Syresham ASTs are:
5.4 In order to assess the actual or outturn effects of the opening of the two improvement schemes, we have produced an Evaluation Summary Table (EST), which mirrors the appearance of the AST, and includes details of the actual sub-objectives that have been evaluated.
5.5 The POPE process concentrates on economy and safety impacts of new schemes at present, but this may be widened to include environmental effects, and guidance is currently being written to outline the best approach for these objectives at present.
5.6 The main points to note on the EST are:
5.7 The environmental aspects of the two A43 schemes have not been evaluated in detail. The main premise for the benefits identified in the AST is that properties along the old A43 will experience a benefit in noise and air quality due to the removal of traffic onto the bypasses, and as the traffic reductions in the two villages have been greater than predicted, it is fair to say that the environmental impacts reported in the AST are likely to have been achieved.
5.8 In terms of negative forecasts such as landscape, Biodiversity and water, no assessment of these sub-objectives have been carried out at present.
5.9 The AST for both the Silverstone and Syresham improvement schemes predicted significant accident savings. In order to evaluate whether these predicted savings are likely we have undertaken an initial evaluation of accident savings accrued for the new schemes.
5.10 Normally, it is usual for accident savings to be evaluated at least three years after opening in order to get a fair reflection in the number of accidents in the corridor, therefore this evaluation for the One Year After Evaluation is an initial view and cannot be considered as a firm conclusion at this time.
5.11 Despite this caveat, we have obtained accident data for 3 years from 2001, i.e. two years prior to scheme opening and a year post scheme opening. Table 5.3 below summarises the accident rates along the A43 from Brackley to Towcester. The Average flows have been taken from a site on the A43 at Brackley.
| Year | Length of road (KM) | Average Flow (AADT) | No. of accidents | Accident Rate (PIA / MVKM) |
|---|---|---|---|---|
| 2001 | 16.1 | 21862 | 44 | 0.342 |
| 2002 (before opening) | 16.1 | 22944 | 48 | 0.356 |
| 2003 | 16.1 | 29267 | 28 | 0.163 |
5.12 The accident rate has dropped from 0.35 personal injury accidents (PIA) per million vehicle kilometres (mvkm) to 0.163 PIA/mvkm. The national average accident rate for a dual carriageway is 0.165 PIA/mvkm, which shows that the improvement schemes has reduced the accident rate to those typical for a road of this type. If higher flows are used for the assessment (for example the AADT at Silverstone is around 32,000), then the observed accident rate has dropped below the national average.
5.13 We do stress again however, that this is a One Year Evaluation, and firm conclusions should really not be derived until at least three years after opening, but the initial signs are that the scheme has been successful in reducing accidents on the A43.
5.14 Atkins have obtained the locations of the observed accidents, and Figures 5.1 and 5.2 show the location of these accidents in 2001 and 2003 respectively.
Figure 5.1 – Accidents along the A43 between Brackley & the A5 at Towcester, in 2001
Figure 5.2 - Accidents along the A43 between Brackley & the A5 at Towcester, in 2003
5.15 These figures clearly show the reduction in the number of accidents on this section of A43. The number of accidents has been reduced from 44 in 2001, to 28 in 2003, a 36% reduction. Figure 5.2 also clearly shows that there are very few accidents on the A43 around the villages of Syresham and Silverstone.
5.16 Within the AST, the predicted accidents savings of the 30 year assessment period have been reported, and in order to provide an initial view on the robustness of these conclusions, we have predicted the number of accidents over the 30 year assessment period.
5.17 In order to do this, we have assumed a conservative 1% growth in traffic each year, and a consistent accident rate of 0.16, also assuming a 30,000 AADT average in 2003, this results in a total of 1686 accidents without the bypass and 984 accidents with the bypass, a saving of 702 accidents over the section, which includes both the Silverstone and Syresham bypasses.
5.18 The proportion of fatal/serious/slight accidents has been determined from figures quoted in COBA 11, i.e. 0.025 fatal, 0.148 serious and 0.827 slight. From COBA 11 we also have the average severity split (that is, the number of fatal, serious and slight casualties per accident). The final accident and casualty figures are shown in the EST.
5.19 This compares well with the prediction of accident savings reported in the two AST’s.
5.20 As outlined in the previous section, Economy impacts are measured by changes in journey times and our new information suggests that these changes are around 6-10 minutes, and when applied to higher traffic growth than originally forecast, then the actual economic benefits are higher than those predicted. For the Silverstone section, the benefits are 50% higher and 77% higher for the Syresham section.
5.21 The Silverstone AST predicted that accessibility benefits would accrue in terms of reduced severance and improved conditions for pedestrians and other modes, and these would result in an 86% reduction in traffic in the town.
5.22 Outturn traffic volumes suggest that 90% of the Silverstone through traffic and 98% of traffic in Syresham has been removed, again suggesting that the accessibility benefits outlined in the AST are fair.
5.23 The AST again states that the scheme facilitates additional development in Brackley as well as further improvements to the Silverstone Motor Race Circuit.
5.24 In terms of Planning Policy within the County and the developments in Brackley, the County has advised that only limited development is currently planned in Brackley, but this will be considered further in the Five-Year After assessment for these schemes.
5.25 Also, the operation of accessing and egressing to/from the F1 weekend was generally reported as being an improvement over preceding years, providing confidence in the continued use of Silverstone as a regular F1 venue.
5.26 A summary of effects across all evaluation sub-objectives are included in the EST’s for Silverstone and Syresham in Tables 5.4 and 5.5 respectively.
6.1 The Highways Agency has a requirement to carry out re-evaluations of trunk road schemes recently implemented by the Department of Transport. The purpose of these re-evaluations is to provide a back check of the levels of benefit accruing from new schemes and to determine how far the department achieves the objectives and benefits it claims from its road programme.
6.2 In summary, the main points to note from the One Year Evaluation of the A43 Silverstone and Whitfield Turn – Brackley Hatch (Syresham) improvements are:
6.3 Evaluation of other sub-objectives within the AST will be carried out as part of the Five-Year After assessment, which will consider accident reductions in more detail, as well as how land use has changed in the area as a result of the A43 Silverstone and Whitfield Turn to Brackley Hatch improvement schemes.