Latest
Home » Road Projects » Area 8 » Road Project
Contact us

by phone or email

Register for
email alerts

On information that's important to you

Feature

Disabled Driver Questionnaire

We want to produce a driver information programme for our disabled customers. To help us produce the best possible guidance, please take a few minutes to fill in our questionnaire.

Feature

Better information for your journey

The National Traffic Control Centre collects real-time information on road conditions.

Quick Links

The Project Control Framework

On 1st April 2008 we launched the Project Control Framework. The Framework sets out how we, together with the Department for Transport, manage and deliver major improvement projects.

Traffic news on your desktop

Helpful ways to access the latest traffic information when you need it.

A1/A14 Brampton Hut Installation of Traffic Signals and Resurfacing

A1/A14 Brampton Hut Installation of Traffic Signals and Resurfacing

Status
Completed
Located in
Area 8Map of the Agency's Operational Areas
Scheme type
OtherRoad Schemes Managed by the Highways Agency

The Project

On 31 July 2006, work started on a scheme to provide traffic signals on the A14, on the roundabout where it passes under the A1. This work improved traffic flow and safety. At the same time, the opportunity was taken to make some other improvements. They were to:

  • widen parts of the roundabout,
  • put a new road surface around the roundabout,
  • improve road signs and markings,
  • provide improved lighting,
  • provide anti-skid surfacing.

Work was completed in December 2006.