The Project Control Framework
On 1st April 2008 we launched the Project Control Framework. The Framework sets out how we, together with the Department for Transport, manage and deliver major improvement projects.
Traffic news on your desktop
Helpful ways to access the latest traffic information when you need it.
Scheme Programme
The award of the Early Contractor Involvement (ECI) Contract was made to Costain Limited on 1 July 2005.
Construction commenced on: 2 September 2006. Completion: December 2007
The following programme summary outlines the key project stages and milestones.
| July 2005 | Contract awarded to Costain Ltd. |
|---|---|
| August 2006 | Start of Work Exhibitions |
| September 2006 | Start construction on the A2/A282 Dartford Improvement |
| September 2006 | Publish Scheme Assessment Report and Environmental Statement for M25 Junction 1b to 3 Widening. Hold Exhibitions |
| June 2007 | Start construction on the M25 Junction 1b to 3 Widening |
| December 2007 | A2/A282 Dartford Improvement complete |
| Summer 2008 | M25 Junction 1b to 3 Widening complete |