The Project Control Framework
On 1st April 2008 we launched the Project Control Framework. The Framework sets out how we, together with the Department for Transport, manage and deliver major improvement projects.
Traffic news on your desktop
Helpful ways to access the latest traffic information when you need it.
Disconnected Pages
Key Stages of Construction
M1 Junction 6a-10 programmed schedule of works
Section (Phase) 1 Works
- North of Junction 10 to South of Junction 9 - complete end of May 2008.
Section (Phase) 2 works
- Southbound carriageway, South of Junction 9 to Junction 6A by June 2008.
- Northbound carriageway, South of Junction 9 to Junction 6A by end July/ early August 2008.
- Central reservation, South of Junction 9 to Junction 6A by the end of November 2008.
- Final overall commisioning and system stabilisation period by December 2008.