Timetable

  • Publish Environmental Statement - 23 August 2007
  • End of comment period on Environmental Statement - 15 November 2007
  • Secretary of State Decision - 12 May 2008
  • Start of Works Junction 16-18 - 27 May 2009 
  • Completion Junction 16-18 - Summer 2010
  • Start of Works Junction 18-21 - Summer 2010
  • Completion Junction 18-21 - Summer 2011
  • Start of Works Junction 21-23 -Summer 2011
  • Completion - Summer 2012