Latest traffic information

Breadcrumb Navigation

You are here:

  1. Home »
  2. Road Projects »
  3. Area 3 »
  4. A3 Hindhead Improvement »
  5. Timetable

Website Navigation

Useful Links

Feature

Better information for your journey

The National Traffic Control Centre collects real-time information on road conditions.

Quick Links

How We Manage Our Roads

In this section you can find out more about how we manage and maintain these roads and plan for the future

The Project Control Framework

On 1st April 2008 we launched the Project Control Framework. The Framework sets out how we, together with the Department for Transport, manage and deliver major improvement projects.

Traffic news on your desktop

Helpful ways to access the latest traffic information when you need it.

Timetable

Programme at a glance

Activity Status
2007
Clear trees and scrub and carry out ecological and archaelogical mitigation works, temporary fencing and site clearance Complete
Construct main project compound Complete
Construct  Boundless to Thursley Link Road for use as a temporary  A3 diversion Complete
Carry out localised earthworks in Boundless Valley Complete
Excavate out tunnel portals and prepare tunnelling compound & equipment Complete
Construct southern part of Canadian Memorial Underpass Complete
 Carry out utility diversions On-going
2008 
Construct Hammer Lane Underpass and junction

Complete and open

Construct northern half of Canadian Memorial Underpass Complete and open
Construct Hazel Grove overbridge and junction Complete and open
Start tunnelling from both north and south portals Complete
Start main earthworks in Boundless Valley Complete
Construct Blackhanger Underpass Complete and open
Open Greensand Way to local traffic Complete and open
2009
Construct new southbound carriageway between the Spaniard and Hazel Grove Complete
Complete tunnel excavation and primary lining   Complete
Excavate deep cutting north of Hazel Grove Complete except near Miss James Bridge
Construct Miss James Footbridge Construction started
Construct tunnel service buildings Structures complete
Complete embankment and bunds in Boundless Valley Complete
Carry out tunnel lining works Complete
2010
Install drainage for new A3 Partially complete
Lay pavement for new A3 Partially complete
Carry out mechanical and electrical installation works along new A3 Planned
Carry out landscaping and planting In progress on completed earthworks areas
Install mechanical and electrical systems in the tunnel Planned
Fully Open new dual carriageway from the Spaniard to Hazel Grove junction Planned
2011
Test tunnel mechanical and electrical systems Planned
Open new A3 Planned
Carry out alterations to existing A3 Planned
Start landscaping and planting Planned
2012
Complete landscaping and planting  Planned