A3 Hindhead Improvement

The project will deliver quicker, more reliable journeys on a safer road.

Traffic news on your desktop

Helpful ways to access the latest traffic information when you need it.

M56 Eastbound Sharston Link Bridge Works

M56 Eastbound Sharston Link Bridge Works

Status
Current
Located in
Area 10Map of the Agency's Operational Areas
Scheme type
OtherRoad Schemes Managed by the Highways Agency
Updates
Get email alerts when we publish new information Get email alerts when we publish new information

The Project

What are we doing?

We are repairing and refurbishing the M56 Junction 3 Sharston Link bridge.

When are we doing it?

Work started on 1st October 2007 and will be completed by 18th June 2008.

Why are we doing it?

To improve the bridge to modern standards and avoid major bridge replacement works in future.

Traffic Management

How will we manage the traffic? 

  • There will be a 40mph speed limit enforced by police cameras
  • We are not planning to close lanes during the daytime
  • There will be some occasional overnight road closures of the M56 Sharston Link
  • We don't expect to have to close the A5103 Princess Parkway
  • Narrow lanes will be in place on the eastbound M56 Sharston Link for the duration of the scheme
  • Narrow lanes will be in place on the M56 (Princess Parkway) above the bridge for 6 weeks during the project.

All road closures and diversion routes will be clearly signed.

Update

Traffic management will be removed on 16th,17th & 18th June. This will mean overnight closures of the M56 eastbound between Junction 3 and Junction 2.