Better information for your journey
The National Traffic Control Centre collects real-time information on road conditions.
How We Manage Our Roads
In this section you can find out more about how we manage and maintain these roads and plan for the future
The Project Control Framework
On 1st April 2008 we launched the Project Control Framework. The Framework sets out how we, together with the Department for Transport, manage and deliver major improvement projects.
Traffic news on your desktop
Helpful ways to access the latest traffic information when you need it.
Construction Progress
A419 Blunsdon Bypass Construction Progress - February 2009
General
Over the last few weeks the weather has allowed us to make good progress.
Southbound Carriageway
The tie in to the north of the southbound carriageway has been finished and is now open to traffic in its final state.
Northbound Carriageway
The road surfacing and kerbing to the tie in of the northbound carriageway off slip near Turnpike Junction is complete, and works continue to the attenuation pond in this area.
Coldharbour Roundabout
Road surfacing where Coldharbour Junction meets Lady Lane Bridge has been completed, kerbs, road markings, verge fill and topsoil in this area continue. Other works due to be carried out during the next few weeks include the assembly of lighting columns.

Bus Turning Area
Verge fill and topsoil, edgings & tactiles are progressing well in this location and will carry on during the coming weeks.
Lady Lane link road
Anti dazzle fencing has been installed between the Lady Lane link road and the northbound dual carriageway.
Down grading to the old A419
Works have progressed well to the down grading of the old A419. Road markings have been put down near Chapel Farm Bridge, footpath surfacing has been laid and the majority of bunds have been top soiled, theses activities will continue during the next few weeks.

The A419 Blunsdon Bypass was opened to traffic at the end of 2008 after just over 2 years of construction. The opening has removed the congestion from the bottlenecks at Lady Lane Junction and Turnpike roundabout and removed through traffic from the existing trunk road through Blunsdon. Other works have been carried out since the opening, mainly on the old section of trunk road, to convert the existing road into a single carriageway