Timetable

Project Dates

Taylors Wood

  • Work started the 6 August 2007
  • Restrictions on carriageway will be implemented from the 28 August 2007
  • Work was completed on 3 November 2007

Temple Grafton to Redhill

  • Work started on the 10 October 2007
  • Work was completed on 3 November 2007