Latest
Home » Road Projects » Area 10 » Road Project
Contact us

by phone or email

Register for
email alerts

On information that's important to you

Feature

Disabled Driver Questionnaire

We want to produce a driver information programme for our disabled customers. To help us produce the best possible guidance, please take a few minutes to fill in our questionnaire.

Feature

Better information for your journey

The National Traffic Control Centre collects real-time information on road conditions.

Quick Links

A3 Hindhead Improvement

The project will deliver quicker, more reliable journeys on a safer road.

Traffic news on your desktop

Helpful ways to access the latest traffic information when you need it.

M56 Junction 14 Drainage Works

M56 Junction 14 Drainage Works

Status
Completed
Located in
Area 10Map of the Agency's Operational Areas
Scheme type
OtherRoad Schemes Managed by the Highways Agency

The Project

This scheme was the second part of the M56 Junction 14 drainage renewal. The drainage in the westbound verge was completely replaced in October 2004.

The drainage network on the eastbound verge and central reserve, had a number of defects which require attention. Without this work, problems would have persisted leading to more regular lane closures.

Work started on 8th October 2007 and was finished by early February 2008.