Disabled Driver Questionnaire
We want to produce a driver information programme for our disabled customers. To help us produce the best possible guidance, please take a few minutes to fill in our questionnaire.
Better information for your journey
The National Traffic Control Centre collects real-time information on road conditions.
The Project Control Framework
On 1st April 2008 we launched the Project Control Framework. The Framework sets out how we, together with the Department for Transport, manage and deliver major improvement projects.
Traffic news on your desktop
Helpful ways to access the latest traffic information when you need it.
A3 Stag Hill Drainage Improvements
A3 Stag Hill Drainage Improvements
- Status
- Completed
- Located in
- Area 3

- Scheme type
- Other

The Project
Drainage improvements have taken place on the A3 near Stag Hill, Guildford, to reduce the risk of standing water on the carriageway.
These works began on 7 January and were completed on 22 February 2008. To minimise the disruption to the travelling public and for the safety of our site staff, works took place overnight between 10.00pm and 6.00am each night. During this time there were overnight lane closures on each carriageway.
A full closure of the northbound carriageway took place from 10.00pm on Saturday 19 January to 2.00pm on Sunday 20 January. During this time drivers followed the signed diversion route. One lane on the southbound carriageway remained open at all times.