Latest
Home » Road Projects » Area 7 » Road Project
Contact us

by phone or email

Register for
email alerts

On information that's important to you

Feature

Better information for your journey

The National Traffic Control Centre collects real-time information on road conditions.

Quick Links

A3 Hindhead Improvement

The project will deliver quicker, more reliable journeys on a safer road.

Traffic news on your desktop

Helpful ways to access the latest traffic information when you need it.

A1(M) Junction 17 Sliproads

A1(M) Junction 17 Sliproads

Status
Current
Located in
Area 7Map of the Agency's Operational Areas
Scheme type
OtherRoad Schemes Managed by the Highways Agency
Updates
Get email alerts when we publish new information Get email alerts when we publish new information

The Project

The Highways Agency is undertaking reconstruction and resurfacing work along the northbound entry slip road and the southbound exit slip road at Junction 17 of the A1 (M).

Work on the northbound entry slip road at Juction 17 began on Tuesday 6th May and was completed on Friday 23rd May 2008. During this period, the northbound entry slip road was closed 24 hours a day in order for the work to be carried out.

Work on the southbound exit slip road at Junction 17 will begin on Wednesday 18th June and is due to be completed by Monday 14th July 2008. During this period, the southbound exit slip road will be closed 24 hours a day in order for the work to be carried out.

Traffic Management

Junction 17 southbound closure:

Traffic wanting to leave the A1 at Junction 17 will continue south to Junction 16 and rejoin the A1(M) northbound to the A1(M) Junction 17 northbound slip to Peterborough.

Non motorway traffic will leave the A1 southbound at Alwalton/Chesterton junction to travel east on the A605 to Alwalton, south on the A1139 Orton Parkway to the A1139 Fletton/Orton Parkway Interchange, then west along Fletton Parkway towards A1 Junction 17.