Latest
Home » Road Projects » Area 11 » Road Project
Contact us

by phone or email

Register for
email alerts

On information that's important to you

Feature

Better information for your journey

The National Traffic Control Centre collects real-time information on road conditions.

Quick Links

The Project Control Framework

On 1st April 2008 we launched the Project Control Framework. The Framework sets out how we, together with the Department for Transport, manage and deliver major improvement projects.

Traffic news on your desktop

Helpful ways to access the latest traffic information when you need it.

A45/A46 Interchange (Festival Island) - Fascia Panel Repairs to Structures

A45/A46 Interchange (Festival Island) - Fascia Panel Repairs to Structures

Status
Completed
Located in
Area 11Map of the Agency's Operational Areas
Scheme type
OtherRoad Schemes Managed by the Highways Agency

The Project

Essential maintenance work to provide secondary fixings to the existing fascia panels of the retaining wall and four bridges situated at this interchange was completed on the 12 July 2008.

All work was carried out overnight when the traffic was less busy, to limit delays to road users. Short local diversion routes were in place for each of the 5 phases of work.

The work started on the 23 June 2008 and was completed two weeks ahead of programme.

The new fixings will safeguard the integrity of the panels, thereby providing a safer environment for road users.