Latest traffic information

Breadcrumb Navigation

You are here:

  1. »
  2. Home »
  3. Road Projects »
  4. Road Projects »
  5. Area 4 »
  6. Road Project

Website Navigation

Useful Links

Quick Links

Map Based Road Projects Finder - Feedback

We are currently piloting a new map based tool to help you find road projects. Please let us know what you think

The Project Control Framework

This framework sets out how we, together with the Department for Transport, manage and deliver major road improvement projects.

A20 Roundhill Tunnel Closures 2012

A20 Roundhill Tunnel Closures 2012

Status
Current
Located in
Area 4Map of the Agency's Operational Areas
Scheme type
OtherRoad Schemes Managed by the Highways Agency
Updates
Get email alerts when we publish new information Get email alerts when we publish new information

The Project

Routine maintenance works in Roundhill Tunnel on the A20 near Folkestone, Kent take place throughout the year to carry out cleaning and safety inspections.

All closures are to be carried out between 20.00hrs and 06.00hrs.

For all closures traffic will be diverted via the A259 and the A260. The programme is subject to change based on circumstances prevailing at the time of the works. Additional closures may become necessary at times during the year and  these will be updated on this page.

Programme details for 2012 are as follows:

February:
  • Monday 6 and Tuesday 7 (westbound)
  • Wednesday 8 and Thursday 9 (eastbound)
April/May:
  • Monday 30 and Tuesday 1 (westbound)
  • Wednesday 2 and Thursday 3 (eastbound)
July:
  • Monday 2 and Tuesday 3 (westbound) 
  • Wednesday 4 and Thursday 5 (eastbound)
October:
  • Monday 22 and Tuesday 23 (westbound)
  • Wednesday 24 and Thursday 25 (eastbound)