The Project Control Framework

This framework sets out how we, together with the Department for Transport, manage and deliver major road improvement projects.

M5 Hard Shoulder Strengthening

M5 Hard Shoulder Strengthening

Status
Completed
Located in
Area 9Map of the Agency's Operational Areas
Scheme type
OtherRoad Schemes Managed by the Highways Agency

The Project

In January 2010, the Highways Agency carried out hard shoulder strengthening works on a section of the M5 in Worcestershire.

The hard shoulder strengthening took place along M5 between Junctions 4a and 5 beginning mid January, with completion on 30th April 2010.

The hard shoulders on motoways were originally constructed to a different standard to the main carriageways and were in need of restructuring and upgrading. In the future they may be used as running lanes.