Latest
Home » Road Projects » Area 2 » Road Project
Contact us

by phone or email

Register for
email alerts

On information that's important to you

Feature

Disabled Driver Questionnaire

We want to produce a driver information programme for our disabled customers. To help us produce the best possible guidance, please take a few minutes to fill in our questionnaire.

Feature

Better information for your journey

The National Traffic Control Centre collects real-time information on road conditions.

Quick Links

A3 Hindhead Improvement

The project will deliver quicker, more reliable journeys on a safer road.

Traffic news on your desktop

Helpful ways to access the latest traffic information when you need it.

M6 Junctions 16-17 Phase 1 Maintenance

M6 Junctions 16-17 Phase 1 Maintenance

Status
Completed
Located in
Area 10Map of the Agency's Operational Areas
Scheme type
OtherRoad Schemes Managed by the Highways Agency

The Project

The Highways Agency carried out maintenance on the carriageway and several bridges between Junctions 16 and 17 of the M6, south of Sand Bach Services, in Cheshire.

Areas of the carriageway had deteriorated over the last few years resulting in frequent emergency repairs. Those patch repairs were no longer adequate to cope with the volume of traffic and certain sections of the motorway needed to be reconstructed. In addition, repairs to a number of bridges were required.

The works started on site at the beginning of June 2005 and were substantially completed By 10 December 2005, six weeks earlier than the advertised completion date of mid January 2006.

We have achieved the following:

Road Renewals

  • resurfacing of 18 km of carriageway and hard shoulder
  • replacement of 7.5 km of safety fencing
  • replacement of 20 km of white lines and reflective road studs
  • reinstatement of the detector loops for monitoring traffic congestion and road surface conditions which are disrupted by the works, and
  • repairs to the motorway drainage

Structures

  • replacement of the piers of one bridge over the motorway
  • extensive concrete repairs for another bridge over the motorway
  • complete renewal of the waterproofing systems and surfacing for the decks of five bridges carrying the motorway, and
  • renewal of safety barrier in the vicinity of all seven bridges

All the works were undertaken as part of the ongoing renewal and maintenance programme for this busy section of the M6 through Cheshire.