Home » Road Projects » Area 3 » A34 Chieveley / M4 Jct 13 Improvement » Programme of Works
Contact us

by phone or email

Register for
email alerts

On information that's important to you

Feature

Better information for your journey

The National Traffic Control Centre collects real-time information on road conditions.

Quick Links

The Project Control Framework

On 1st April 2008 we launched the Project Control Framework. The Framework sets out how we, together with the Department for Transport, manage and deliver major improvement projects.

Traffic news on your desktop

Helpful ways to access the latest traffic information when you need it.

Programme of Works

A34 Chieveley / M4 Jct 13 Improvement

Programme

Progress and Forthcoming Programme

The main event has been the awarding of the contract. Early works have focused on site clearance, ecological surveys, archaeological excavation, topographical surveys, additional ground investigation, initial topsoil stripping and establishment of the site compound.

The next three months will see the commencement of the A34 bulk earthworks after archaeological and ecological mitigation measures have been undertaken. Works to the M4 will include enabling works such as communication cable diversions and temporary slip road diversions together with temporary motorway widening to facilitate a major traffic management scheme to construct the M4 underpass.

The scheme will be substantially complete by summer 2004, well ahead of the Highways Agency's target.

Outline

Major Works for the construction of the improvement to the A34 commenced on site in May 2003 and incorporate:

  • New 3km A34 dual carriageway which will pass under the M4
  • New slip roads from the new A34 to M4 Junction 13
  • New access arrangements to the service station, maintenance depot and hotel
  • Seven new bridges
  • Major maintenance of 3km of the M4

Programme

Award10th March 2003
Enabling WorksMarch 2003 - May 2003
A34 EarthworksMay 2003 - October 2003
A34 RoadworksMay 2003 - July 2004
A34 BridgeworksJune 2003 - April 2004
M4 RefurbishmentMay 2003 - November 2003
Bussocks Wood Bridge DemolitionNovember 2003
Bussocks Wood Bridge ErectionJanuary 2004
Substantial CompletionJuly 2004
LandscapingNovember - March 2003 and October 2004

Scheme Completion

Value£38.5m
DurationSubstantial completion in 70 weeks
Completion DateSummer 2004