A34 Chieveley / M4 Jct 13 Improvement
Programme
Progress and Forthcoming Programme
The main event has been the awarding of the contract. Early works have focused on site clearance, ecological surveys, archaeological excavation, topographical surveys, additional ground investigation, initial topsoil stripping and establishment of the site compound.
The next three months will see the commencement of the A34 bulk earthworks after archaeological and ecological mitigation measures have been undertaken. Works to the M4 will include enabling works such as communication cable diversions and temporary slip road diversions together with temporary motorway widening to facilitate a major traffic management scheme to construct the M4 underpass.
The scheme will be substantially complete by summer 2004, well ahead of the Highways Agency's target.
Outline
Major Works for the construction of the improvement to the A34 commenced on site in May 2003 and incorporate:
- New 3km A34 dual carriageway which will pass under the M4
- New slip roads from the new A34 to M4 Junction 13
- New access arrangements to the service station, maintenance depot and hotel
- Seven new bridges
- Major maintenance of 3km of the M4
Programme
| Award | 10th March 2003 |
|---|---|
| Enabling Works | March 2003 - May 2003 |
| A34 Earthworks | May 2003 - October 2003 |
| A34 Roadworks | May 2003 - July 2004 |
| A34 Bridgeworks | June 2003 - April 2004 |
| M4 Refurbishment | May 2003 - November 2003 |
| Bussocks Wood Bridge Demolition | November 2003 |
| Bussocks Wood Bridge Erection | January 2004 |
| Substantial Completion | July 2004 |
| Landscaping | November - March 2003 and October 2004 |
Scheme Completion
| Value | £38.5m |
|---|---|
| Duration | Substantial completion in 70 weeks |
| Completion Date | Summer 2004 |