On 1st April 2008 we launched the Project Control Framework. The Framework sets out how we, together with the Department for Transport, manage and deliver major improvement projects.
Traffic news on your desktop
Helpful ways to access the latest traffic information when you need it.
Disconnected Pages
Traffic Management Programme
00001
A1089 Marshfoot Interchange to Asda Roundabout
Traffic Management Programme
- Friday 29th October From Midnight
- Lane 2 closure in each direction
- Monday 1st November From Midnight
- Start preparing contraflow
- Tuesday 2nd November From 7pm until Thursday 18th November at 7am
- Northbound carriageway closed with contraflow on the Southbound carriageway
- Friday 12th November From 8pm until Saturday 13th November at 6am
- Full Northbound closure - follow signed diversion route
- Thursday 18th November From 7am until Wednesday 8th December at 8pm
- Southbound carriageway closed with contraflow on the Northbound carriageway
- Friday 3rd December From 8pm until Monday 6th December at 4am
- Full Southbound closure - follow signed diversion route
- Wednesday 8th December at 11pm until Friday 17th December at midnight
- Lane 2 closure in each direction
These details are correct at time of printing but may change due to unforeseen circumstances.