The Project Control Framework
On 1st April 2008 we launched the Project Control Framework. The Framework sets out how we, together with the Department for Transport, manage and deliver major improvement projects.
Traffic news on your desktop
Helpful ways to access the latest traffic information when you need it.
The Bypass
A10 Wadesmill to Colliers End Bypass
Comments and further information
The Contract was awarded to a Fitzpatrick and Lafarge Joint Venture on the 15th February 2002.
Design work is progressing and construction work has commenced with general site clearance.
The improvement is being constructed for the Highways Agency, an Executive Agency of the Department of Transport, Local Government and the Regions.
The Employer's Agent for the Highways Agency is Mott Macdonald who will undertake a monitoring and certification role.
URS are the Contractor's Designer and will be responsible for the detailed design and supervision of the construction of the Works.
A full-time Community Liaison Officer, Shaun Rowberry, will be based on site throughout the contract and will ensure that scheme activities are considerate of the local community. In partnership with the Highways Agency, Shaun will also produce project leaflets and organise further exhibitions as the scheme progresses. Shaun can be contracted on 01920 823714.
During the construction period should you have any queries or complaints, or require any information with respect to the construction works, please contact:
Community Liaison Officer
Shaun Rowberry
Fitzpatrick Lafarge Joint Venture
Site Offices
Junction A10/A120
Puckeridge
Hertfordshire
SG11 1SA
Telephone: 01920 823714