Home » Road Projects » Area 9 » M6 J6 Thornbridge, Witton and Gravelly Hill Viaducts » Partial Closure
Contact us

by phone or email

Register for
email alerts

On information that's important to you

Feature

Better information for your journey

The National Traffic Control Centre collects real-time information on road conditions.

Quick Links

The Project Control Framework

On 1st April 2008 we launched the Project Control Framework. The Framework sets out how we, together with the Department for Transport, manage and deliver major improvement projects.

Traffic news on your desktop

Helpful ways to access the latest traffic information when you need it.

Partial Closure

M6 J6 Thornbridge, Witton and Gravelly Hill Viaducts

The Purpose of the Works:

To repair fifteen concrete substructures at and to the North West of the M6 Motorway, Junction 6 (Spaghetti Junction). This is part of the Highways Agency's ongoing maintenance and repair programme on the elevated sections of the M6 Motorway.

The Works comprise:

  • Erection of temporary support steelwork,
  • Traffic management to facilitate safe progress of the works,
  • Concrete repairs to the deteriorated elements of the crossbeams,
  • Replacement of bridge bearing plinths,
  • Installation of cathodic protection systems.

Traffic Management:

To ensure the safety of the general public and workforce carrying out the project, traffic management is needed on the motorway slip roads and local roads in the Thornbridge, Witton and Gravelly Hill areas.

The area of Moor Lane in Witton that runs under the M6 Motorway will be closed to through traffic for the duration of the Works. Access to all properties will be maintained throughout the duration of the works and local diversion routes will be clearly signed. Access to Brookvale Trading Estate will be maintained either via College Road or Brookvale Road. Pedestrian access along Moor Lane will be maintained at all times and temporary pedestrian crossing points will be provided.

The closure of the section of Moor Lane directly beneath the M6 Motorway viaduct at Witton will come into effect on Monday 27 October 2003 and is anticipated to last for 32 months.

View larger image in a popup window

Back to Top

Diversion Route:

Phase 1 (21 months)

Northbound traffic on Brookvale Road intending to use Moor Lane will be diverted along The Ridgeway to College Road.

Southbound traffic on College Road intending to use Moor Lane will be diverted along The Ridgeway to Brookvale Road. Access to the Brookvale Trading Estate will be from the Brookvale Road end of Moor Lane.

Phase 2 (from July/August 2005)

As Phase 1 except access to the Brookvale Road Trading Estate will be from the College Road end of Moor Lane.

Back to Top

The Highways Agency are carrying out these works in partnership with AmeyMouchel acting as Construction Manager and the following specialist contractors:

  • Dew Construction
  • General Civils
  • Interserve Project Services
  • Concrete Repairs
  • Balvac Whitley Moran
  • Cathodic Protection
  • Alfred McAlpine
  • Traffic Management

The scheme was designed by Atkins on behalf of the Highways Agency in consultation with Birmingham City Council.

*
M6 Junction 6 (Spaghetti Junction)

For further information call the Highways Agency's Information Line: 08457 50 40 30