Latest traffic information

Breadcrumb Navigation

You are here:

  1. »
  2. Home »
  3. Road Projects »
  4. Road Projects »
  5. Area 9 »
  6. M40 Jct 15 (Longbridge) »
  7. Timetable

Website Navigation

Useful Links

Quick Links

Map Based Road Projects Finder - Feedback

We are currently piloting a new map based tool to help you find road projects. Please let us know what you think

The Project Control Framework

This framework sets out how we, together with the Department for Transport, manage and deliver major road improvement projects.

Timetable

M40 Jct 15 (Longbridge)

 
Event Date
Scheme enters Targeted Programme of Improvements (now known as Programme of Major Schemes) July 2003
Contract Tendered May 2005
Ecological Surveys (Discovery of Bat Roost on Original Alignment) Summer 2005
Public Information Exhibition of revised scheme November 2005
Draft Orders and Environmental Statement published July 2006
Draft Orders Exhibition 21st and 22nd July 2006
Public Inquiry Starts 13th March 2007
Detailed Design Spring 2007
Construction Starts March 2008
Open to Traffic 14th December 2009
Scheme Completed 18th June 2010