Home » Road Projects » Area 10 » M60 Jct 5 to 8 (formerly M63 Jct 6 to 9) Widening » Photo gallery » Photo gallery
Contact us

by phone or email

Register for
email alerts

On information that's important to you

Feature

Better information for your journey

The National Traffic Control Centre collects real-time information on road conditions.

Quick Links

The Project Control Framework

On 1st April 2008 we launched the Project Control Framework. The Framework sets out how we, together with the Department for Transport, manage and deliver major improvement projects.

Traffic news on your desktop

Helpful ways to access the latest traffic information when you need it.

Photo gallery

M60 Jct 5 to 8 (formerly M63 Jct 6 to 9) Widening

Photo Gallery

Demolition of Existing Structures

There are many existing structures to be demolished within the widening scheme. These comprise of 11 bridges, 1 subway and 23 portal sign gantries. By mid August 2004, 2 of the bridges have been demolished (Rutland Lane Footbridge and the Mersey South Slip Bridge at Junction 7) together with 15 no. steel sign gantries. These works have been carried out overnight during full closures of the relevant sections of the motorway with fully signed diversion routes in operation.

Removal of the Mersey South Slip Road Bridge at Junction 7 was carried out by means of a controlled explosive demolition.

Junction 7 Clockwise Off Slip Bridge Prior to Demolition

Junction 7 Clockwise Off Slip Bridge Prior to Demolition

Demolition of Junction 7 Clockwise Off Slip Bridge (07/08/04)

Demolition of Junction 7 Clockwise Off Slip Bridge (07/08/04)

Removal of Debris at Junction 7 Clockwise Off Slip Bridge

Removal of Debris at Junction 7 Clockwise Off Slip Bridge

Demolition of a Steel Portal Sign Gantry

Demolition of a Steel Portal Sign Gantry