Disabled Driver Questionnaire
We want to produce a driver information programme for our disabled customers. To help us produce the best possible guidance, please take a few minutes to fill in our questionnaire.
Better information for your journey
The National Traffic Control Centre collects real-time information on road conditions.
A3 Hindhead Improvement
The project will deliver quicker, more reliable journeys on a safer road.
Traffic news on your desktop
Helpful ways to access the latest traffic information when you need it.
M11 Junction 4 Lighting Refurbishment
M11 Junction 4 Lighting Refurbishment
- Status
- Completed
- Located in
- Area 5

- Scheme type
- Other

The Project
The lighting system on the slip/link road of the M11 Junction 4 and the main line of the M11 up to Luxborough Lane Overbridge northwards was nearing its life expectancy and required replacing and upgrading. The works comprised of the removal and replacement of the existing lighting columns and cables in this location with a new and upgraded system.
Traffic Management
Safety cameras limited traffic to 40mph through the roadworks as they straddled the 70/50mph change in speed limit at the bottom of the M11.
Traffic management also involved various lane closures, with some local diversions necessary where works coincided with a slip road. These were clearly signed, with at least 2 weeks advance notice.
Noise pollution was monitored, and the local enviromental health authority agreed noise limits which the contractor adhered to.