Latest traffic information

Breadcrumb Navigation

You are here:

  1. »
  2. Home »
  3. Road Projects »
  4. Road Projects »
  5. Area 11 »
  6. Road Project

Website Navigation

Useful Links

Quick Links

Map Based Road Projects Finder - Feedback

We are currently piloting a new map based tool to help you find road projects. Please let us know what you think

The Project Control Framework

This framework sets out how we, together with the Department for Transport, manage and deliver major road improvement projects.

M6 Jct 4 to Jct 3 Warwickshire MS3 & MIDAS Phase 3

M6 Jct 4 to Jct 3 Warwickshire MS3 & MIDAS Phase 3

Status
Completed
Located in
Area 11Map of the Agency's Operational Areas
Scheme type
OtherRoad Schemes Managed by the Highways Agency

The Project

Infrastructure works are now complete on a £3.9 million contract to improve the motorway communication system on the M6 between Junctions 3 and 4.

Installation of overhead signal gantries took place during March and April under a series of overnight motorway closures so as to minimise disruption to the travelling public.

Electronic Message Signs installed on the overhead gantries have now been commissioned and all signals are currently operational.

The new signals will be operated from the Highways Agency's West Midlands Regional Control Centre. Operators in the control centre will allocate Traffic Officers and other emergency services to incidents, manage and monitor traffic and control electronic signs on the roads.

MIDAS commissioning has been successfully completed and is now operational.

Further information on Regional Control Centres and Electronic Message Signs is available in the Knowledge Centre section of the web site.