Latest
M11 Essex | Northbound | Overturned vehicle, road closed   ...   A1 Newcastle upon Tyne | Southbound | Heavy traffic   ...   A12 Essex | Northbound | Heavy traffic   ...   A19 North Tyneside | Northbound | Heavy traffic   ...   M25 Essex | Clockwise | Heavy traffic   ...   M60 Greater Manchester | Clockwise | Heavy traffic   ...   M25 Hertfordshire | Clockwise | Multi-vehicle accident, 1 lane closed   ...   M25 Essex | Anticlockwise | Emergency roadworks   ...   M25 Essex | Anticlockwise | Heavy traffic   ...   M1 Nottinghamshire | Northbound | Multi-vehicle accident, 1 lane closed   ...   M621 West Yorkshire | Westbound | Heavy traffic   ...   A595 Cumbria | Northbound | Heavy traffic   ...   A1 Nottinghamshire | Southbound | Heavy traffic   ...   M3 Hampshire | Westbound | Multi-vehicle accident, 1 lane closed   ...   M11 Essex | Northbound | Incident, 1 lane closed   ...   M4 Berkshire | Eastbound | Broken down vehicle, 1 lane closed   ...   A174 Redcar and Cleveland | Eastbound | Heavy traffic | Clear   ...   M20 Kent | Westbound | Accident | Clear   ...   M4 Berkshire | Westbound | Heavy traffic | Clear   ...   A595 Cumbria | Southbound | Heavy traffic   ...   M62 East Yorkshire | Westbound | Accident, 1 lane closed   ...   A174 Redcar and Cleveland | Westbound | Heavy traffic   ...   M1 West Yorkshire | Southbound | Broken down vehicle | Clear   ...   M62 West Yorkshire | Westbound | Heavy traffic   ...   M58 Lancashire | Eastbound | Heavy traffic   ...   M6 Cheshire | Northbound | Heavy traffic | Clear   ...   M6 Cheshire | Northbound | Heavy traffic   ...   M1 Derbyshire | Northbound | Heavy traffic   ...   A1 Bedfordshire | Northbound | Heavy traffic   ...   
Home » Road Projects » Area 6 » A47 Thorney Bypass » Publications » July progress report
Contact us

by phone or email

Register for
email alerts

On information that's important to you

Feature

Better information for your journey

The National Traffic Control Centre collects real-time information on road conditions.

Quick Links

The Project Control Framework

On 1st April 2008 we launched the Project Control Framework. The Framework sets out how we, together with the Department for Transport, manage and deliver major improvement projects.

Traffic news on your desktop

Helpful ways to access the latest traffic information when you need it.

July progress report

July progress report

July Progress Report

Construction work on the Thorney Bypass is now progressing at full speed with in excess of 100 workers on site. The Link Road at the East End was opened on Sunday 3rd July. This allowed the old section of the A47 to be excavated ready for the new road.

Work is also ongoing on the 3 roundabouts. The east and west roundabouts will be open in advance of the Bypass over the next two to three months.

Duke of Bedford School Visit

On the 12th and 13th of July we were visited by Pupils from The Duke of Bedford School.

They witnessed several areas of the site including the concrete batcher and the slipform paver, which is laying the concrete road.

The slipforming operation is now well underway with up to 250m of carriageway being laid each day.