Latest traffic information

Breadcrumb Navigation

You are here:

  1. Home »
  2. Road Projects »
  3. Area 12 »
  4. M1 Jct 30 to end (A1) and M621 »
  5. Publications »
  6. Contents »
  7. Contents

Website Navigation

Useful Links

Feature

Better information for your journey

The National Traffic Control Centre collects real-time information on road conditions.

Quick Links

How We Manage Our Roads

In this section you can find out more about how we manage and maintain these roads and plan for the future

The Project Control Framework

On 1st April 2008 we launched the Project Control Framework. The Framework sets out how we, together with the Department for Transport, manage and deliver major improvement projects.

Traffic news on your desktop

Helpful ways to access the latest traffic information when you need it.

Contents

2.2.2 Syndicate Group 2 - Environment & Integration

Leeds Stakeholder Workshop

2.2.2 Syndicate Group 2 - Environment & Integration

Job Title Organisation
Assistant Route Manager Highways Agency
Route Manager Highways Agency
Project Manager Hyder Consulting Limited
Transport Planning Advisor Leeds Bradford Airport
Transport Planner WYPTE

Group findings were as follows:

  1. Function K also applies to Section 5
  2. Redefine J and K to clarify difference between peak hour, longer distance commuting and more local "utility" trips
  3. Remove I from Section 8
  4. Re-write G: "Provide a major transport link between the regional centres of population AND employment, tourism, recreational areas AND national and international transport gateways"
  5. Strategic functions could be changed to National functions
  6. New national function - provides access to national events/venues and attractions within the region
  7. Future Functions: New regional function to provide access to multi-modal transport interchanges
  8. Future Functions: Agree with Strategic and Regional having priority over local functions but local demand management can only be implemented if sustainable.

Environment Issues

Noise complaints are an issue over all of the populated network
Has Air Quality Management Area in Leeds been declared?
Biodiversity Action Plan (BAP) - does Yorkshire Link have one?
BAP - how is it to be delivered outside of TPI?

Additional Environmental outcome:

Use of recycled (sustainable) materials to be encouraged - 1 rating

Integration Issues

Lack of signing to existing opportunities e.g. Supertram terminal/park&ride at Crossgates (A64)
Lack of Park & Ride and share facilities

Environment Options
Option No. Option Description Some Advantages Some Disadvantages Rating

OE1

Develop and implement Route Landscape Management Plans

Better co-ordinate resources

Requires maintenance of Management Plans

Requires revision and more input to planning process

1

OE2

Develop and implement Route Biodiversity Action Plans

Better co-ordinate resources

Requires maintenance of Action Plans

1

OE3

Low noise surfacing

Reduces road traffic noise

Note: 50% of M1/M621 Already covered

 

1

OE4

Work with Local Authorities to improve air quality (particularly in Air Quality Management Areas)

Reduces concentration of air pollution by managing location of congestion

 

1

OE5

Permanent speed limit to improve air quality

   

1

OE6

Investigate use of targeted planting to improve air quality

   

2

OE7

VMS signing of poor air quality

   

1

OE8

Demand management/ATM linked to air quality

   

1

Integration Options
Option No. Option Description Some Advantages Some Disadvantages Rating

OG1

Strategy to encourage and

formalize the use of park and

share

Help to facilitate park and ride schemes, hence reduce total number of vehicles on the road at concentrated locations

Better co-ordinate drivers destination, without wandering around to locate parking space

Expand destination of drivers, i.e. multiple P&S sites instead of one town centre

Park and share may not be favoured by drivers unless priority for high occupancy vehicles is provided. Hence limited effect on the total numbers.

Park and share sites need to be well lit, secure, and well maintained.

Land required for site

1

OG2

Park and ride at service areas

Help to facilitate park and ride schemes, hence reduce total number of vehicles on the road at concentrated locations

Better co-ordinate drivers destination, without wandering around to locate space

Maximise utilisation of existing facilities, without additional manning or services

Drivers may not be willing to pay the parking costs

Service areas may not have room for this facility

1

OG3

Park and ride at key junctions

Help to facilitate park and ride schemes, hence reduce total number of vehicles on the road at concentrated locations

Better co-ordinate drivers destination, without wandering around to locate space

Park and ride may not be favoured by drivers unless priority for high occupancy vehicles is provided. Hence limited effect on the total numbers.

Park and share sites need to be well lit, secure, and well maintained.

Land required for site

1

OG4

Bus / coach services plus bus stops at service areas

Maximise utilisation of existing facilities, without additional manning or services

Bus/ coach will be same in congested area unless dedicated lanes are provided to ensure journey time reliability

1