Latest
Home » Road Projects » Area 3 » Road Project
Contact us

by phone or email

Register for
email alerts

On information that's important to you

Feature

Better information for your journey

The National Traffic Control Centre collects real-time information on road conditions.

Quick Links

A3 Hindhead Improvement

The project will deliver quicker, more reliable journeys on a safer road.

Traffic news on your desktop

Helpful ways to access the latest traffic information when you need it.

M3 Junction 3 Lightwater Interchange

M3 Junction 3 Lightwater Interchange

Status
Completed
Located in
Area 3Map of the Agency's Operational Areas
Scheme type
OtherRoad Schemes Managed by the Highways Agency

The Project

Maintenance work on the M3 Junction 3 Lightwater Interchange is complete it started on 9 October 2006 and was completed by Christmas 2006.

This was the final phase and consisted of repairing the two inner parapets of the interchange.

Traffic Management

The work took place behind vertical concrete barriers which were installed to ensure the safety of the workforce.

Work was carried out overnight, between the hours of 9.00pm – 5.00am Monday to Saturday, due to the daytime traffic levels at this busy interchange. Only one lane was in operation during the work period.  To minimise the impact of the works on the public we specifically designed to keep all lanes open during peak times.

Lane closures took place during off peak daytime hours for material deliveries and removal of spoil. Any delays in traffic, or increase in noise during the works were minimal.

The West Bridge footpath was closed for the duration of the work. A signed footpath diversion was in place with all pedestrians being diverted via East Bridge footpath.