Disabled Driver Questionnaire
We want to produce a driver information programme for our disabled customers. To help us produce the best possible guidance, please take a few minutes to fill in our questionnaire.
Better information for your journey
The National Traffic Control Centre collects real-time information on road conditions.
The Project Control Framework
On 1st April 2008 we launched the Project Control Framework. The Framework sets out how we, together with the Department for Transport, manage and deliver major improvement projects.
Traffic news on your desktop
Helpful ways to access the latest traffic information when you need it.
M50 Jct 1 to M5 Junction 8 Carriageway Resurfacing Works
M50 Jct 1 to M5 Junction 8 Carriageway Resurfacing Works
- Status
- Completed
- Located in
- Area 9

- Scheme type
- Other

The Project
A 2 mile - 3 km stretch of carriageway between the M50 Junction 1 and M5 Junction 8 has been resurfaced. This included the roundabout at Junction 8 of the M5.
The resurfacing scheme, started on 21st January 2006, for a duration of 20 weeks, provided the opportunity to replace the safety barriers and to widen the hard shoulders enhancing safety for drivers involved in emergencies and unscheduled stops. Improvements were also made to the embankment and drainage systems.
The Highways Agency used low noise surfacing on this scheme.
This project was procured via the Construction Management Framework. Find out more about this type of procurement.
Benefits
Now the works are completed, the main benefits are:
- Restoration of the carriageway to a high standard.
- Upgraded safety barriers and wider hard shoulders.
- Reduced maintenance works in future years.