Disabled Driver Questionnaire
We want to produce a driver information programme for our disabled customers. To help us produce the best possible guidance, please take a few minutes to fill in our questionnaire.
Better information for your journey
The National Traffic Control Centre collects real-time information on road conditions.
The Project Control Framework
On 1st April 2008 we launched the Project Control Framework. The Framework sets out how we, together with the Department for Transport, manage and deliver major improvement projects.
Traffic news on your desktop
Helpful ways to access the latest traffic information when you need it.
Timetable
Below are anticipated dates and main details about each phase of the works:
| Phase 1 | 24 April - 22 May | Widening the north east carriageway |
| Phase 2 | 23 May - 20 June | Widening the south west carriageway |
| Phase 3 | 21 June - 30 June | Construction of centre islands and pedestrian |
| Phase 4 | 1 July - 3 July | Resurfacing of junction |
| Phase 5 | 4 July - 15 July | Installation of traffic signals and anti-skid works |