A1 Leeming to Barton Improvement

Project status:   Current


Start date:   Early 2014
End date:  Mid 2017


Type:   Major Scheme
help icon

Major Scheme

Part of our programme of improvements (value >10m)

Cost:  £380 million


-

Draft Orders (Catterick Lane / Tunstall Road) published on 17 April 2014

Draft orders have been published for an alternative alignment to the ‘2013 Made Orders’ scheme for the local road network in the vicinity of the Catterick Lane / Tunstall Road junction. The draft orders are open for objection between 17 April 2014 and 28 May 2014, further information regarding the objection process is documented in the public notices. Copies of the draft orders documents are available under Publications.

Temporary Road Works in April 2014

A series of temporary road works will take place in April, in preparation for the main construction works starting. There will be various overnight lane closures on the A1 and two way traffic lights on local roads in  April.From 4 April  there will be overnight  closures on the A1 between Catterick North and Catterick South junctions, reducing to 50mph and narrow lanes during the Easter period. Please visit the Journey Impact Page.

Start of Works

A start of works exhibition was held at Catterick Racecourse on Friday 21 March 2014 and on Saturday 22 March 2014 .

Made Orders (Leeming to Scotch Corner) published on 21 November 2013

Orders for the section between Leeming and Scotch Corner were made in October 2013.

Copies of the Made Orders documents are available under Publications.

Public Inquiry for Draft Supplementary Orders (Scotch Corner to Barton section) in February 2014

  • The Inquiry for the draft supplementary Orders, published on 18 July 2013, for the Scotch Corner to Barton section is now closed.
  • The Planning Inspectorate report will be published as soon as it is available.
  • Copies of the Public Inquiry deposit documents are available under Publications.

What is happening?

In December 2012 the Chancellor of the Exchequer delivered his Autumn Statement to Parliament announcing the decision to proceed with the remaining section of the A1 Dishforth to Barton scheme, between Leeming and Barton. We are now developing the design of this section of the A1.

When and where is this happening?

Preparation for main construction works are now underway on the A1 between Leeming A1(M) junction 51 and Barton A1(M) junction 56 in North Yorkshire. The temporary traffic regulation order comes into force on 3 April 2014 allowing us to install traffic management, including reduced speed limits and narrow lanes, on the A1. The first section of the A1 to have traffic management installed will be between Catterick North and Catterick South junctions.

Why is this happening and what will it cost?

The 12 mile section of the A1 between Leeming and Barton carries between 59,000 to 69,000 vehicles per day. It has poor alignment with many side road junctions, farms and field accesses. The accident rate is broadly in line with the national average for older dual carriageways, but the severity ratio is significantly higher. Incidents often lead to full closure of the route with lengthy diversions. This is the only section of non-motorway on the strategic M1/A1(M) route between London and Newcastle.

The estimated final outturn of £380 million was approved by the Secretary of State in January 2014 prior to the start of construction in March 2014.

How will the scheme be carried out?

The A1 Leeming to Barton upgrade will replace the existing dual carriageway with a new three lane motorway. It will also include the provision of a new Local Access Road alongside the new motorway, improving safety for local traffic from the surrounding communities. Access to the strategic road network will be via a new grade separated junction at Catterick and an improved junction at Scotch Corner.

What are the benefits?

The primary objective of the project is to improve safety and to improve journey time reliability between London and major urban centres in the north of England and Scotland.

How do I find out more information ?

More information will be posted on this project page as it becomes available. You can subscribe to be alerted when updates are made.

If you have any queries about this project you should contact the Highways Agency Information Line by emailing ha_​info@​highways.​gsi.​gov.​uk or calling 0300 123 5000.

Email us at: A1​LeemingtoBarton@​highways.​gsi.​gov.​uk

Write to us at: A1 Leeming to Barton Project Team, Major Projects North, Highways Agency, Piccadilly Gate, Store Street, Manchester, M1 2WD (telephone 0161 930 5759)

Or at: A1 Leeming to Barton Site Office, Leases Farm Quarry, Leases Bridge, Leeming Bar, Northallerton, DL8 1DU

Details of scheduled roadworks are provided to help you plan your journey. Please note that works are weather- and resource- dependent and may need to be cancelled at short notice. This information is not updated in real time so please check Traffic England for current traffic conditions. Diversion timings are approximate and act as a guide only.

Will there be roadworks?

Yes.

There will be various overnight lane closures on the A1 and two way traffic lights on local roads in April.

During April there will be overnight closures on the A1 between Catterick North and Catterick South junctions, reducing to 50mph and narrow lanes during the Easter period.

Road Works

DateDurationDetailsAllow an Extra
27/03/2014 to 16/04/20148pm to 6am weekdays onlyClosure of A1 lane 2 northbound between Catterick South junction and Catterick North junction for installation of traffic management equipmentN/A
07/04/2014 to 16/04/20148pm to 6amClosure of A1 southbound between Catterick North junction and Catterick South junction for installation of traffic management equipment. A diversion route will be signed via A61363 to 4 minutes
07/04/2014 to 16/04/20148pm to 6am weekdays onlyClosure of A1 lane 2 northbound between Catterick South junction and Catterick North junction for installation of traffic management equipment N/A
10/04/2014 to 31/03/201724 hoursBoth directions of the A1 between Catterick North and Catterick South junctions-Narrow Lanes with 50mph speed limit with Average Speed Camera detectionN/A
12/04/2014 to16/04/20148pm to 6amA1 Northbound lane closures Catterick South to Catterick junctionsN/A
14/04/2014 to 15/04/20148pm to 6am weekdays onlyClosure of A1 lane 1 southbound between Catterick North junction and Barton junction for surveying N/A
14/04/2014 to 16/04/20149am to 4pmBridge Road Two way temporary traffic lights for Site access constructionN/A
14/04/2014 to 16/04/20149am to 4pmA6108 Two way temporary traffic lights for Site access construction N/A
14/04/2014 to 25/04/2014Weekdays only between 9am and 4pmMiddleton Tyas Lane Two way temporary traffic lightsN/A
14/04/2014 to 11/05/2014Weekdays between 9pm to 4am(Overnight)A1 Southbound closed Catterick North to Catterick South junctions (Diversion via A6136 Catterick Village) It is to undertake temporary widening of the southbound carriageway into the cental reserve prior to the new construction work commencing to the east of the A1. N/A
22/04/2014 to 23/04/20149am to 4pmLeases West Roundabout.Outer lane of roundabout closureN/A
22/04/2014 to 25/04/20149am to 4pmStation Road Two way temporary traffic lights for Site access construction.N/A
22/04/2014 to 11/05/20148pm to 6amA1 Northbound lane closures Catterick South to Catterick junctionsN/A

How will you manage traffic?

Two way traffic lights are temporary.

Where lane closures are required we will use traffic cones and temporary speed limits where appropriate.

Traffic management equipment may include narrow lanes, road cones, reduced speed limits, CCTV and cameras.

Will there be diversions?

Clearly signed diversion routes will be in place for road closures.

A1(M) Leeming to Barton Diversion Route Map (121KB PDF)

For single lane closures the roads will remain open, so no diversion route is required.

ActivityDate
Detailed designJanuary 2013 to March 2014
Public Inquiry for supplementary draft Orders (Scotch Corner to Barton section) 4 February 2014
Start of works exhibition at Catterick RacecourseFriday 21st March 2014 and Saturday 22nd March 2014
Start of construction works (Leeming to Scotch Corner section)March 2014
Middleton Tyas-Scurragh House Lane. Local access road improvementsSpring/Summer 2014
Leeming Junction to Bowbridge Lane. Local access road improvementsSpring 2014-Autumn 2014
Catterick-Brompton. Earthworks and A1 mainline improvementsSpring 2014-Spring 2017
A1 mainline improvements-Leeming Junction to Leases Lane NorthboundSummer 2014-Summer 2015
Local Access Road Crossing at Lords Lane. New bridge constructionAutumn 2014-Winter 2015
Sowber Hill Farm. New accommodation bridge constructionAutumn 2014-Summer 2015
Construction of new Tunstall Bridge. Construction of Tunstall BridgeAutumn 2014-Summer 2015
A6108 Richmond Road. New roundabout openSpring/Summer 2015
Brompton North and Bormpton South Bridges.Brompton North and South.Bridge replacementSummer 2015
A1 mainline improvements-Leeming Junction to Leases Lane SouthboundSummer 2015-Spring 2016
Local Access Road-Catterick North to Scotch Corner. Local access road improvementsSummer 2015-Winter 2015/2016
Catterick Central Junction. New Catterick Central Junction openAutumn/Winter 2015
A6136 Fort Overbridge replacementAutumn 2015-Winter 2016/2017
Scotch Corner junction improvementsAutumn/Winter 2015
Catterick South Juction.Catterick South junction closureSpring 2016
Leases Lane to Catterick Central Junction. New off line motorway section openSpring/Summer 2016
Scotch Corner to BartonSubject to Public Inquiry

Leaflet

A1 Leeming to Barton Improvement - Public Exhibition Materials
A1 Leeming to Barton Improvement - Public Exhibition Materials - February 2013

Legal

A1 Leeming to Barton Improvement - Draft Orders (Catterick Lane / Tunstall Road) - 17 April 2014
Copies of the draft orders for the Catterick Lane / Tunstall Road alternative.
A1 Leeming to Barton (Scotch Corner to Barton section) Public Inquiry Notice of alternative routes
Public Inquiry Notice of alternative routes for A1 Leeming to Barton(Scotch Corner to Barton section)
A1 Leeming to Barton (Scotch Corner to Barton section) Public Inquiry Notice to submit alternative routes
Public Inquiry Notice to submit Alternative routes for A1 Leeming to Barton (Scotch Corner to Barton section)
A1 Leeming to Barton - Public Inquiry Deposit Documents (Scotch Corner to Barton section)
 A1 Leeming to Barton - Deposit documents for Public Inquiry (Scotch Corner to Barton section)
A1 Leeming to Barton Improvement - Secretary of State decision letter (Leeming to Scotch Corner section) - 23 October 2013
Decision letter stating the positive decision regarding the A1 Leeming to Barton improvement scheme and agreement to publish the draft orders for the Leeming to Scotch Corner section
A1 Leeming to Barton - Notice of intent to hold a Public Inquiry (Scotch Corner to Barton section) - 27 September 2013
Notice of intent to hold a Public Inquiry for the A1 Leeming to Barton (Scotch Corner to Barton section)
A1 Leeming to Barton Improvement - Draft Supplementary Orders (Scotch Corner to Barton section) - 18 July 2013
Links to all documents (excluding the Environmental Assessment Report) and public notices published on 18 July 2013 for the draft supplementary Orders (Scotch Corner to Barton section).

Plan

A1 Leeming to Barton Improvement - Scheme Plan
A1 Leeming to Barton Improvement - Scheme Plan