M27 Junction 3 Improvements

Project status:   Current

Start date:   December 2014
End date:  August 2015

Type:   Improvement Scheme
help icon

Improvement Scheme

Part of our programme of improvements (generally with value <£10m)

Cost:  £2.3 million

Managed by:   Area 3


The main construction is now complete.

Additional tasks, including landscaping, will be carried out over the coming weeks using overnight closures.


What is happening?

We will be carrying out work to improve the interchange where the M271 junction 2 meets the M27 at junction 3. This will include:

  • widening of the M27 westbound exit slip-road to 3 lanes
  • widening of the M271 northbound and southbound approaches to the interchange to three lanes
  • removal of the eastern overbridge hard shoulder to allow three lanes
  • adding traffic signals to the interchange

These works are part of the national Pinch Point Programme. The Pinch Point Programme forms part of the UK Government's growth initiative, outlined during the Chancellor’s Autumn Statement in November 2011.

View the Scheme Overview Plan for more information.

When and where is this happening?

Main construction began in January 2015 and is expected to be complete by the end of August  2015.

The scheme is located at junction 3 of the M27, to the north-west of Southampton.

Why is this happening and what will it cost?

The M27 junction 3 is a major route into Southampton and the Docks. The junction currently suffers from significant congestion on both the northbound and southbound approaches of the M271 and the M27 westbound exit slip road during peak periods.

This congestion and delay has a detrimental impact upon current economic activity, and will continue to restrict and discourage economic opportunities and the potential for growth within the surrounding area..

The works will cost approximately £2.3 million.

How will the scheme be carried out?

The work will be carried out during both night and day shifts. There will be overnight closures of sections of the interchange, with signed diversion routes, to allow work to be carried out safely. During the day, there will be speed restrictions and narrow lanes at the interchange.

Narrow lane traffic management will be in place with speed limits.

Please allow additional time for your journey.

What are the benefits?

As part of the Pinch Point Programme, this scheme aims to:

  • help to reduce daily congestion, particularly during peak hours
  • reduce journey times for the travelling public
  • boost the economic growth of the area
  • improve safety at the motorway interchange

How do I find out more information ?

More information will be posted on this project page as it becomes available. You can subscribe to be alerted when updates are made.

If you have any queries about this project you should contact the Highways Agency Information Line by emailing ha_​info@​highways.​gsi.​gov.​uk or calling 0300 123 5000.

Details of scheduled roadworks are provided to help you plan your journey. Please note that works are weather- and resource- dependent and may need to be cancelled at short notice. This information is not updated in real time so please check Traffic England for current traffic conditions. Diversion timings are approximate and act as a guide only.

Will there be roadworks?

The main construction is now complete.

Additional tasks, including landscaping, will be carried out over the coming weeks. Please be aware of the following overnight (10pm to 4am) planned closures.

Road Works

DateDurationDetailsAllow an Extra
Monday 21 September10pm to 4amM27 junction 3 eastbound exit slip roadPlease allow extra time for your journey
Wednesday 23 and Thursday 24 September10pm to 4amM271 southbound (between A3057 Romsey Road roundabout and M27 junction 3)Please allow extra time for your journey
Friday 25 September10pm to 4amM27 junction 3 northern section of roundaboutPlease allow extra time for your journey
Monday 28 and Tuesday 29 September10pm to 4amM271 southbound (between M27 junction 3 and M271 junction 1)Please allow extra time for your Journey
Tuesday 29 and wednesday 30 September10pm to 4amM27 junction 3 southern section of roundaboutPlease allow extra time for your journey
Wednesday 30 September and Thursday 1 October10pm to 4amM27 junction 3 western overbridgePlease allow extra time for your Journey
Friday 2 and Monday 5 October10 pm to 4amM271 northbound (between Redbridge roundabout and M27 junction 3)Please allow extra time for your journey

How will you manage traffic?

Narrow lane traffic management with a 50mph speed limit will be introduced on the M27 junction 3 westbound exit slip road, on the roundabout and on the M271 approach roads to the junction.

The work will require some overnight closures (10pm-6am) of sections of the slip roads, approach roads and the roundabout.

Signed diversion routes will be in place during these times.

Please allow additional time for journeys using junction 3.

Will there be diversions?

During closures, clearly signed diversion routes will be in place.

The diversion route south of M27 junction 3 will be via A35, A326 and junction 2. North of M27 junction 3, the diversion route will be via the A3057, A3090, A36 and junction 2.

Please see map for details.