A27 Middle Farm to Selmeston Resurfacing

Project status:   Completed


Start date:   21 January 2013
End date:  12 February 2013


Type:   Maintenance Scheme
help icon

Maintenance Scheme

Part of our ongoing programme of work to maintain England's strategic road network

Cost:  £583,000


Managed by:   Area 4

-

Where was the project located?

Work took place between Middle Farm and Selmeston, east of the junction with the A26, in East Sussex.

Why was the scheme needed?

The work was required because our studies showed that the road surface in the area had deteriorated and the road markings had faded. Signage was nearing the end of its functional life.

What work was carried out?

We resurfaced the road and installed new warning signs, road studs and road markings on the A27 Lewes Road.

How did this benefit road users?

The resurfacing work has provided a smoother, quieter carriageway and improved safety for road users. The signage and road marking work will reduce the risk of personal injury collisions occuring on this section of the A27.