A453, M1 Junction 24 Roundabout Resurfacing

Project status:   Completed
Region:  Midlands


Start date:   26 November 2012
End date:  December 2012


Type:   Maintenance Scheme
help icon

Maintenance Scheme

Part of our ongoing programme of work to maintain England's strategic road network

Cost:  £350,000


Managed by:   Area 7

-

Where was the project located?

We resurfaced the roundabout at junction 24 of the M1, in late November 2012.

Why was the scheme needed?

The road surface had become damaged and the white lines had faded through deterioration.

What work was carried out?

We resurfaced the roundabout and renewed the lines, traffic signal loops and road markings.

How did this benefit road users?

Benefits of carrying out this work are that it will now prolong the life of the roundabout and improve safety for drivers.