M6 Junction 10a-13: Smart Motorway

Project status:   Current
Region:  Midlands


Start date:   31 October 2013
End date:  Spring 2015


Type:   Major Scheme
help icon

Major Scheme

Part of our programme of improvements (value >10m)

Cost:  £87.5 million


-

Scheme Newsletter

We are producing a series of newsletters in which we will provide updates on the construction of the M6 Junction 10a-13 smart motorways scheme. You can download the latest  newsletter from the Publications page.

 

Current progress

Our works in the verges of the motorway are continuing with good progress being made. The narrow lanes and 50 mph speed restriction remain in place for the duration of the works for safety reasons. Our construction programme has been carefully planned to minimise disruption to road users.

Works are continuing in the verge/hardshoulder. We have:

  • Installed new sign and signal gantries
  • Removed old unnecessary signs and supports
  • Reconstructed the hardshoulders between junctions 12 and 13

We Are:

  • Completing construction of emergency refuge areas (ERAs)
  • Completing installation of new drainage
  • Erecting new safety fences
  • Erecting new signs

 

We are now commencing works in the central reserve. This involves adjusting the layout of the narrow lanes to give working space next to the central reserve barrier. New drainage and ducts will be constructed.

See Journey Impact for more information.

What is happening?

We are working to improve the M6 by making it a "smart motorway" between junctions 10a and 13. Smart motorways (previously known as managed motorways) help relieve congestion by using technology to vary speed limits. They also allow the hard shoulder to be used as a running lane to create additional capacity. They deliver these benefits at a significantly lower cost than conventional motorway widening and with less impact on the environment during construction. Find out more about smart motorways.

When and where is this happening?

Advanced enabling works started in September 2013 and full construction began on 31 October 2013. This is ahead of the original construction start date, which was planned for between January and March 2014. For more information please visit our Current Delivery Programme page.

This Smart Motorway scheme will be carried out on the M6 between junctions 10a-13, located near Stafford and Cannock.

Why is this happening and what will it cost?

The M6 between Birmingham and Manchester is a strategic route that carries high volumes of heavy goods and other vehicles. Congestion and unreliable journey times are already being experienced at busy periods and traffic is predicted to continue to grow.

The M6 meets a number of important high level needs:

  • It is part of the Trans-European Network of Roads (Route E5)
  • It is part of the national motorway network making a major contribution to the UK economy
  • It forms an integral part of the main transport corridor connecting the Midlands with the north west, south west and south east of England, Scotland and Wales
  • It is a major transport link for the movement of freight and other strategic traffic
  • It facilitates the movement of holiday traffic and access to national events

The estimated outturn cost of this scheme is £87.5 million.

How will the scheme be carried out?

This project has two distinct sections:

  • Junctions 10a-11a

    This section between M54 at junction 10a and the M6 Toll at junction 11a will have the benefit of controlled motorway technology which uses gantry signing to control lane discipline and speeds.  Hard shoulder running will not be provided over this section. The new works will provide dedicated slip road lanes at the interchanges with M54 and M6 Toll. This will help accommodate the high flows expected to enter and leave the M6 at these motorway interchanges.

  • Junctions 11a-13

This section from the M6 Toll to Stafford will have permanent hard shoulder running as well as the technology to vary mandatory speed limits.

During all works, average speed cameras will be used through the length of the scheme for the safety of both the road user (motorists) and the workforce. Also, temporary CCTV cameras will be used to monitor for broken down vehicles and other incidents.

A number of information signs and signals on gantries will be installed as part of the improvement scheme. Some existing vegetation within the highway boundary has been removed to make space for the new infrastructure. Replacement planting will be provided, where possible, around the new infrastructure.

The main works are planned to be done Monday to Friday during normal working hours. However, there will be a significant amount of work which needs to be carried out overnight and during road closures. This is because during the day the working space is limited and not all operations can be done safely. At night, when traffic flows are considerably lighter, lanes can be temporarily closed.

Works that we are carrying out are as follows:

  • Providing new overhead gantries and refurbishing existing gantries.
  • Providing new information signs, variable message signs and signals.
  • Providing new emergency refuge areas.
  • Improving carriageway and drainage.
  • Providing new fencing at Penkridge.
  • Reconstructing the hardshoulder between junctions 12 and 13.

We will endeavour to do all works, whether during the day or at night, with the minimal amount of disruption and disturbance. If we are planning to carry out works overnight near to people’s homes, we will communicate with them in advance.

What are the benefits?

This project will relieve congestion and smooth the flow of the traffic, improving safety and journey times. These benefits will also support economic development in the region.

We already have evidence of the benefits that a smart motorway scheme can bring. The first smart motorway scheme opened to traffic on the M42 motorway in 2006. Recent analysis of the data gathered since opening has found that journey time reliability improved by 22 per cent and reduced emissions by up to 10 per cent, due to traffic flowing more smoothly.

In addition, personal injury accidents have reduced by more than half (55.7%) since hard shoulder running was introduced. There was also an overall reduction in the severity of accidents with zero fatalities and fewer seriously injured.

How do I find out more information ?

More information will be posted on this project page as it becomes available. You can subscribe to be alerted when updates are made.

If you have any queries about this project you should contact the Highways Agency Information Line by emailing ha_​info@​highways.​gsi.​gov.​uk or calling 0300 123 5000.

Carillion are the Highways Agency’s contractor for the M6 J10a-13 works. Their stakeholder management team will be available throughout the construction process to answer any queries you may have about the project. They can be contacted (Monday to Friday 8am to 5pm) at M6​J1​0​A-​1​3​@​carillionplc.​com

Details of scheduled roadworks are provided to help you plan your journey. Please note that works are weather- and resource- dependent and may need to be cancelled at short notice. This information is not updated in real time so please check Traffic England for current traffic conditions. Diversion timings are approximate and act as a guide only.

Will there be roadworks?

Yes, roadworks will be needed to allow us to carry out works safely:

  • hard shoulder closures are in place throughout the length of the scheme to give access to the works
  • lane closures and full carriageway closures will be required, but these will only be at times of reduced traffic flow or at night time
  • from October 2014 works are being undertaken in some sections of the central reserve - this wil require carriageway closures overnight whilst we reposition the narrow lanes and details will be added to this website. The 50 mph speed limit will remain

Additional Works on the M6

The Highways Agency are currently involved in a number of works along the M6 which may also affect your journey.  Please follow the links below if you would like further details regarding these works.

 

Road Works

DateDurationDetailsAllow an Extra
Friday 24 October10pm-8amM6 southbound junction 13 to 12 – lanes 2 and 3 closed and junction 12 to 11 – lanes 1 and 2 closed45 mins
Friday 24 October10pm-8amM6 northbound junction 12 - lanes 1 and 2 closed between slip roads. Junction 12 northbound on slip road closed45 mins
Monday 27 October10pm-6amM6 southbound junction 13 to 12 - lanes 2 and 3 closed. Junction 12 to 11 - lanes 1 and 2 closed. Junction 11 southbound off slip road closed45 mins
Monday 27 October10pm-6amM6 northbound junction 11a to 12 - lanes 1 and 2 closed. Junction 12 northbound off slip road closed.45 mins
Tuesday 28 October10pm-6amM6 southbound junction 13 to 12 - lanes 2 and 3 closed. Junctions 12 to 10a - lanes 1 and 2 closed. Junction 11 southbound on slip road closed. Junction 11 southbound off slip road closed.45 mins
Tuesday 28 October10pm-6amJunction 11A to 12 – lanes 1 and 2 closed.45 mins
Wednesday 29 October10pm-6amM6 southbound junction 13 to 12 - lanes 2 and 3 closed45 mins
Wednesday 29 October10pm-6amM6 northbound junction 10a-12 - lanes 1 and 2 closed. Junction 11 northbound on slip closed. Junction 11 northbound off slip road closed.45 mins
Thursday 30 October10pm-6amM6 southbound junction 13 to 12 - lanes 2 and 3 closed45 mins
Thursday 30 October10pm-6amM6 northbound junction 11 to 11a - lanes 1 and 2 closed. Junction 11 northbound on slip closed.45 mins
Friday 31 October10pm-8amM6 southbound junction 13 to 12 - lanes 2 and 3 closed45 mins
Friday 31 October10pm-8amM6 northbound junctions 10A to 11 – lanes 1 and 2 closed45 mins
Saturday 1 November10pm-10amM6 northbound junction 12 on slip road closed and junction 12 – lanes 1 and 2 closed between slip roads45 mins
Sunday 2 November10pm-5.30amM6 southbound junctions 13 to 12 - lanes 1 and 2 closed. Junction 12 southbound on slip road closed45 mins
Monday 3 November10pm – 6amM6 southbound junction 13 to 12 - full closure45 mins
Tuesday 4 November10pm – 6amM6 southbound junction 13 to 12 - full closure45 mins
Wednesday 5 November10pm – 6amM6 southbound junction 13 to 12 – lanes 1 and 2 closed45 mins
Wednesday 5 November10pm – 6amM6 northbound junction 10A to 11 full closure45 mins
Thursday 6 November10pm – 6amM6 southbound junction 13 to 12 – lanes 1 and 2 closed45 mins
Thursday 6 November10pm – 6amM6 northbound junction 10A to 11A full closure45 mins
Friday 7 November10pm – 8amM6 southbound junction 13 to 12 - full closure45 mins
Saturday 8 November10pm – 10amM6 southbound junction 13 to 12 – lanes 1 and 2 closed. Junction 12 southbound on slip road closed45 mins
Saturday 8 November10pm – 10amM6 northbound junction 12 northbound on slip road closed45 mins

How will you manage traffic?

During the day three narrow lanes will be kept open in each direction for the duration of the works. A 50 mph speed restriction is in place to protect roadworks and road users. Lane closures and carriageway closures will be carried out overnight.

The hard shoulder is closed with the use of cones and temporary steel barriers which give protection to the workforce from errant vehicles.

A free vehicle recovery service will be provided within the road works. In the event of a breakdown the stranded vehicle can be identified quickly and the free vehicle recovery service dispatched to take motorists and their vehicle to a safe location. CCTV cameras will be monitored by a dedicated team in a control room, who will promptly identify incidents and notify vehicle recovery teams to assist stranded motorists.

Will there be diversions?

The M6 southbound carriageway will be closed over several nights. Diversion routes will be signed as follows:

Southbound

For M6 traffic: from M6 junction 12
A5 westwards to Gailey roundabout,
A449 south to M54 junction 2,
M54 to rejoin M6 at junction 10A.

For M6 Toll traffic: from M6 junction 12
A5 westwards to M6 Toll junction T7.

Northbound

Exit at M6 at junction 10a

M54 to junction 2

A449 northwards to Gailey roundabout

A5 eastwards to M6

Drivers should allow an extra 45 minutes for their journey.

Diversion route map

Business Case

M6 Junctions 10A-13 Managed Motorway Business Case
M6 Junction 10A - 13 Managed Motorway - Business Case - Information correct as at December

Leaflet

M6 Junction 10a-13 Managed Motorway - Public Exhibition 2013
Information about the public exhibition on Friday 26 and Saturday 27 July 2013 for the M6 Junction 10a-13 Managed Motorway.

Legal

M6 Junction 10a-13 Managed Motorway - Notice of Determination - July 2013
M6 Junction 10a-13 Managed Motorway - Notice of Determination - July 2013

Newsletter

M6 Junction 10a-13 Smart Motorway Newsletter - March 2014
Welcome to the first in a series of newsletters in which we will provide updates on the construction of the M6 Junctions 10a to 13 smart motorways scheme.

Report

M6 Junction 10a-13 Managed Motorway - Environmental Assessment Report
Environmental Assessment Report for the M6 Junction 10a-13 Managed Motorway scheme.